From: Jennifer Cline

Sent: Mon Jun 29 15:11:49 2015

To: Heather Penni

Cc: Dan Huff

Subject: RE: Stowers & Grange

Importance: Normal

Attachments: image002.gif;

 

image

Hi - We have to pay the full amount. Change Orders are not necessary if a bid item exists and the City accepts the work.

However, there are SDC’s available to use. I gave you a print out for Stowers, Grange and Heintz, and there is an additional $25K per year that can be used for sidewalks only (if that was not already applied).

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Heather Penni [mailto:hpenni@cityofmolalla.com]

Sent: Monday, June 29, 2015 3:04 PM

To: 'Dan Huff'; 'Jennifer Cline'

Subject: Stowers & Grange

Hi!

Have we determined what is the final payment amount? Need to cut that check by tomorrow or the capital project rolls into next year……………no bueno!

Thanks

HP