From: Jennifer Cline
Sent: Mon Jun 29 15:11:49 2015
To: Heather Penni
Cc: Dan Huff
Subject: RE: Stowers & Grange
Importance: Normal
Attachments: image002.gif; Hi - We have to pay the full amount. Change Orders are not necessary if a bid item exists and the City accepts the work. However, there are SDC’s available to use. I gave you a print out for Stowers, Grange and Heintz, and there is an additional $25K per year that can be used for sidewalks only (if that was not already applied). Jennifer Cline, P.E. City of Molalla Public Works Director O: 503.759.0218 F: 503.829.3676 From: Heather Penni [mailto:hpenni@cityofmolalla.com] Sent: Monday, June 29, 2015 3:04 PM To: 'Dan Huff'; 'Jennifer Cline' Subject: Stowers & Grange Hi! Have we determined what is the final payment amount? Need to cut that check by tomorrow or the capital project rolls into next year……………no bueno! Thanks HP