From: Jennifer Cline
Sent: Tue Mar 31 08:32:28 2015
To: hai@curran-mcleod.com
Subject: RE: Stowers - Storm and Subgrade Issues
Importance: Normal
Hi Hassan,
I will be giving this to Dan this morning for signature. Hope to have it returned to you soon.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]
Sent: Tuesday, March 31, 2015 6:17 AM
To: Jennifer Cline
Subject: FW: Stowers - Storm and Subgrade Issues
Please see the attached cost for replacing the storm line. Let us know what you think.
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com
From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]
Sent: Monday, March 30, 2015 4:25 PM
Subject: RE: Stowers - Storm and Subgrade Issues
Hi Hassan,
Here you go, let me know if you have any questions.
Thanks
Curtis
From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]
Sent: Monday, March 30, 2015 6:31 AM
To: Curtis Cooksey
Cc: Jennifer Cline; hpenni@cityofmolalla.com
Subject: FW: Stowers - Storm and Subgrade Issues
Hi Curtis,
I hope you enjoyed your time off.
Can you send me a price to replace the existing concrete storm pipe with 10” ductile iron as shown on the attached map. The pipe is very shallow and partially in the subgrade. It shouldn’t take a lot of efforts to do.
Fabric over the subgrade where directed by the City will be paid at the price of $1.20 as per your February 11th (10:09 am),e-mail.
Jennifer, we need to quantify the subgrade stabilization, it is 88/CY to include excavation, material disposal, fabric and rock replacement.
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Friday, March 27, 2015 5:10 PM
To: Hassan Ibrahim
Cc: Heather Penni
Subject: Stowers - Storm and Subgrade Issues
Hi Hassan,
Quick update on Stowers:
I decided to replace the storm line with 10” Ductile Iron. I do not want to take the risk of the line shattering under compaction with the vibratory roller with less than a foot of cover. A change order will need to be requested for the cost. I’m not 100% sold that it needs to be the entire length, but certainly to catch basin mid-way. See attached.
I also watch the proof-roll. I saw rutting but no sign of the ground pumping. I requested fabric be placed for separation between the subgrade and rock. This will be an added cost by the unit price as submitted by Curtis for Stowers.
The curb line should be over excavated at least 1-foot to the storm drain. It sound like the $88/sy includes the excavation and additional rock placed back. Does this seem reasonable if the cost of rock is included with the over-excavation for stabilization?
Feel free to give me a call on Monday.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676