From: Jennifer Cline

Sent: Tue Jan 20 10:33:50 2015

To: Craig Cantrell

Cc: Garrett Edmunds; Nicolas Lennartz

Subject: RE: Sidewalk inspection

Importance: Normal

 

Hi Craig,

We were able to inspect both homes with the exception to the driveway cross slope. This was due to the lace of curb and gutter. Please let us know when the properties will be ready for final inspection.

Also we noticed that some of the adjoining gutter drains have reverse slope through the sidewalk. This may be a drainage issue in the future for the homeowners is debris flows into the drains and create a clog.

Sincerely,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Craig Cantrell [mailto:craig@cityredevelopment.com]

Sent: Monday, January 19, 2015 11:36 PM

To: jcline@cityofmolalla.com

Subject: Sidewalk inspection

Please inspect in the AM

Lot 13 149 finneys Ave, Molalla Oregon 97038

Lot 14

660 patrol

660 patrol may have been inspected last week.

Concrete is scheduled for early AM.

Please Call with any questions 503 380-5072.

Best regards.