From: Jennifer Cline
Sent: Tue Jan 20 10:33:50 2015
To: Craig Cantrell
Cc: Garrett Edmunds; Nicolas Lennartz
Subject: RE: Sidewalk inspection
Importance: Normal
Hi Craig,
We were able to inspect both homes with the exception to the driveway cross slope. This was due to the lace of curb and gutter. Please let us know when the properties will be ready for final inspection.
Also we noticed that some of the adjoining gutter drains have reverse slope through the sidewalk. This may be a drainage issue in the future for the homeowners is debris flows into the drains and create a clog.
Sincerely,
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Craig Cantrell [mailto:craig@cityredevelopment.com]
Sent: Monday, January 19, 2015 11:36 PM
To: jcline@cityofmolalla.com
Subject: Sidewalk inspection
Please inspect in the AM
Lot 13 149 finneys Ave, Molalla Oregon 97038
Lot 14
660 patrol
660 patrol may have been inspected last week.
Concrete is scheduled for early AM.
Please Call with any questions 503 380-5072.
Best regards.