From: Jennifer Cline
Sent: Tue Sep 15 17:39:21 2015
To: Christine Hein; Phillip Bender
Cc: Amy Barreto; Mark Strandberg; Lee, Rob
Subject: RE: RFP for CCTV
Importance: Normal
Hi,
Thank you for sharing. It’s the first time I’ve seen that report.
Jennifer Cline, P.E. | Public Works Director
Licensed in OR, WA
117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038
O: 503.759.0218 | F: 503.829.3676
From: Christine Hein [mailto:CHein@ringbenderlaw.com]
Sent: Tuesday, September 15, 2015 2:27 PM
To: Jennifer Cline <jcline@cityofmolalla.com>; Phillip Bender <PBender@ringbenderlaw.com>
Cc: Amy Barreto <abarreto@ringbenderlaw.com>; Mark Strandberg <MStrandberg@ringbenderlaw.com>; Lee, Rob <roblee@BrwnCald.com>
Subject: RE: RFP for CCTV
Jennifer-
Following up on this message you sent to Phil, regarding the highlighted sentence below, the 2014 annual report (attached) says that some work was done. Wanted to share in case you didn’t have a copy.
Best Regards,
Tina
Christine L. Hein
Ring Bender LLLP
Direct: 503.964.6726
Cell: 503.314.0958
Please consider the environment before printing this e-mail.
-----Original Message-----
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Tuesday, September 15, 2015 10:37 AM
To: Phillip Bender
Cc: Amy Barreto; Christine Hein; Mark Strandberg; Lee, Rob
Subject: RE: RFP for CCTV
Hi Phil,
Regarding your comments 3 & 4. These bullet items were taken directly from the Executive Summary of the Molalla Wastewater Facilities Plan (WWFP). See page ES-2 of the attached. I have no evidence that any I & I work was completed in the City since the WWFP was completed in 2000.
Chapter 6 even recommends not doing anything on the bottom of page 6-5. We know I & I work was completed prior to 2000, but not since. The grouting conditions would be at least the same, possibly worse today.
I've also included Chapter 6 that covers the collection systems. Table
6.1 provides data from a completed flow monitoring analysis completed in 1999. The January 22 storm events does show surcharging in several locations. Since this study, Big Meadows has built out completely and there have been other areas of growth. On the map (Figure 6-1) provided I don't see Safeway or the other industrial collection lines.
I will make the changes below, let me know if you would still like me to reword those bulleted items.
Thanks,
Jennifer Cline, P.E. | Public Works Director Licensed in OR, WA City of Molalla <http://www.cityofmolalla.com/>
117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038
O: 503.759.0218 | F: 503.829.3676
-----Original Message-----
From: Phillip Bender [mailto:PBender@ringbenderlaw.com]
Sent: Tuesday, September 15, 2015 9:02 AM
To: Jennifer Cline <jcline@cityofmolalla.com>
Cc: Amy Barreto <abarreto@ringbenderlaw.com>; Christine Hein <CHein@ringbenderlaw.com>; Mark Strandberg <MStrandberg@ringbenderlaw.com>; Phillip Bender <PBender@ringbenderlaw.com>
Subject: Re: RFP for CCTV
Jennifer,
I reviewed and have a couple comments and questions on the RFP:
1. Page 1, second paragraph of section 2, Background. "The lesser of
the
system flows from the south side of the City and drains along Highway 211/Main St, diverting at Bear Creek and onto the WWTP" should be revised to read as follows: "The lesser portion of thesystem flows from the south side of the City along Highway 211/Main St to a location near Bear Creek, where it turns and flows into the WWTP."
2. Page 1, third paragraph of section 2, Background. "Whether" should
be
changed to "weather".
3. Page 1, bullets to third paragraph. How do we know the following?
"A
significant portion of the previous I/I reduction work (grouting) work has exceeded its useful life and has failed." Where does this information come from? Do we have direct evidence that it "has failed"? I suggest rewriting this sentence to read, "Previous I/I reduction work (grouting) has now exceeded its design life."
4. Page 1, bullets to third paragraph. How do we know the following?
"Facilities are generally hydraulically overloaded during winter storm events." Where does this conclusion come from? All facilities are hydraulically overloaded? I did not understand this to be the case. What about saying, "Certain locations within the collection system can become hydraulically overloaded during winter storm events" or something similar?
5. WWTP line. It is not clear from the WWTP plan drawings or
descriptions
that the Bear Creek outfall from Bear Creek up as close to or into the WWTP is included in the RFP. It needs to be. The Consent Decree requires us to inspect from the outfall up the outfall line.
Let me know if any of my comments don't make sense or you want to discuss.
Let me know what the answers are to the questions.
Thanks.
Phil
Phillip M. Bender - Partner
925 Liberty Ave., 8th Floor
Pittsburgh, PA 15222
(412) 770-7721
Ring Bender McKown & Castillo LLLP
This transmission is intended for the sole use of the individual or entity to whom it is addressed, and may contain information that is privileged, confidential and exempt from disclosure under applicable law. You are hereby notified that any dissemination, distribution or duplication of this transmission by someone other than the intended addressee or its designated agent is strictly prohibited. If your receipt of this transmission is in error, please notify this firm immediately by telephone at
(503) 964-6730, or reply to this transmission. Thank you.
On 9/14/15 7:52 PM, "Jennifer Cline" <jcline@cityofmolalla.com> wrote:
>Hi Phil,
>
>Have you had a chance to look over the RFP? I would like to post it on
>Wednesday if you think it looks good.
>
>Thanks,
>
>Jennifer Cline, P.E. | Public Works Director
>
>Licensed in OR, WA
>
>City of Molalla <http://www.cityofmolalla.com/>
>
>117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038
>
>O: 503.759.0218 | F: 503.829.3676
>
>-----Original Message-----
>From: Phillip Bender [mailto:PBender@ringbenderlaw.com]
>Sent: Wednesday, September 09, 2015 7:15 PM
>To: Jennifer Cline <jcline@cityofmolalla.com>
>Cc: Lee, Rob <roblee@BrwnCald.com>; Christine Hein
><CHein@ringbenderlaw.com>; Dan Huff <dhuff@cityofmolalla.com>
>Subject: Re: RFP for CCTV
>
>I'll take a look and let you know.
>
>Phillip M. Bender
>Ring | Bender
>(412) 770-7721
>
>> On Sep 9, 2015, at 5:25 PM, Jennifer Cline <jcline@cityofmolalla.com>
>wrote:
>>
>> Hi Phil,
>>
>> I just completed a final draft of the RFP for the CCTV Work as
>identified in our I/I plan. See attached.
>>
>> In the plan is an updated map of the storm system at the WWTP. I
>> have
>identified several storm lines to inspect. What is your take on the
>current plan for inspection? Do you feel there is more identified than
>needed?
>>
>> If you have any other comments, please let me know.
>>
>> Thanks,
>>
>> Jennifer Cline, P.E. | Public Works Director Licensed in OR, WA City
>> of Molalla<http://www.cityofmolalla.com/>
>> 117 N Molalla Ave. | PO Box 248 . |Molalla, OR 97038
>> O: 503.759.0218 | F: 503.829.3676
>> [X]<http://www.cityofmolalla.com/>
>> <Draft_RFP_CCTV_Sanitary Sewer.pdf>
>