From: Jennifer Cline

Sent: Thu Jan 21 15:42:09 2016

To: Evan Goepferd

Cc: Chris Link; Dan Huff

Subject: RE: Projects Bidding:// City of Molalla - Molalla Avenue Improvements â Urban Renewal

Importance: Normal

 

Hi Evan,

The goal was to accomplish as many projects as possible, however funding will not be available to continue with the remaining projects you have identified below.

Regards,

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Evan Goepferd [mailto:evan@weitmanexcavation.com]

Sent: Thursday, January 21, 2016 2:55 PM

To: Jennifer Cline <jcline@cityofmolalla.com>

Subject: RE: Projects Bidding:// City of Molalla - Molalla Avenue Improvements – Urban Renewal

Good afternoon Jennifer. I called and left a tele message as well.

When will the following project be out for bid / expected start dates?

Molalla Avenue - Bid Due: 27-JAN-2016 @ 11:00AM [Wednesday]

Shaver Avenue - Unknown

Hart Avenue - Unknown

West 3rd Street - Unknown

Thank you.

Evan Goepferd

Estimator / Project Manager

Weitman Excavation, LLC

Office: 11225 SW Clay Street, Sherwood, OR 97140

Cell: 503.452.2539 • Work: 503.682.3322 • Fax: 503.682.3366

www.weitmanexcavation.com

From: Chris Link [mailto:Chris.Link@msa-ep.com]

Sent: Thursday, January 21, 2016 2:30 PM

To: Evan Goepferd <evan@weitmanexcavation.com>; Jennifer Cline <jcline@cityofmolalla.com>

Cc: Betsy Cook <Betsy.Cook@msa-ep.com>

Subject: RE: Projects Bidding:// City of Molalla - Molalla Avenue Improvements – Urban Renewal

Hi Evan – Please contact Jennifer Cline with the City of Molalla about the City’s other projects.

Chris Link, P.E. | Civil Engineer, Associate

Licensed in OR, WA

T: 541.741.2975 | Cell: 503.869.4885 | Chris.Link@msa-ep.com

777 High Street, Suite 200 | Eugene, Oregon 97401 | www.msa-ep.com

Murray, Smith & Associates, Inc. | Your Public Works Partner

Notice: This e-mail and any attached files are the private confidential property of the sender, and the materials are privileged communications intended solely for the receipt, use, benefit and information of the intended recipient indicated above. If you are not the intended recipient, you are hereby notified that any review, disclosure, copying, distribution, or taking of any other action in reliance on the contents of this transmission is strictly prohibited, and may result in legal liability on your part. If you have received this e-mail in error, please notify us immediately at the above address.

P Please consider the environment before printing this e-mail.

From: Evan Goepferd [mailto:evan@weitmanexcavation.com]

Sent: Thursday, January 21, 2016 2:21 PM

To: Chris Link <Chris.Link@msa-ep.com>; Betsy Cook <Betsy.Cook@msa-ep.com>

Subject: RE: Projects Bidding:// City of Molalla - Molalla Avenue Improvements – Urban Renewal

When will the following project be out for bid / expected start dates?

Molalla Avenue - Bid Due: 27-JAN-2016 @ 11:00AM [Wednesday]

Shaver Avenue - Unknown

Hart Avenue - Unknown

West 3rd Street - Unknown

Thank you.

Evan Goepferd

Estimator / Project Manager

Weitman Excavation, LLC

Office: 11225 SW Clay Street, Sherwood, OR 97140

Cell: 503.452.2539 • Work: 503.682.3322 • Fax: 503.682.3366

www.weitmanexcavation.com

From: Chris Link [mailto:Chris.Link@msa-ep.com]

Sent: Tuesday, January 12, 2016 3:28 PM

To: Evan Goepferd <evan@weitmanexcavation.com>

Subject: RE: Projects Bidding:// City of Molalla - Molalla Avenue Improvements – Urban Renewal

Received. Thanks!

Chris Link, P.E. | Civil Engineer, Associate

Licensed in OR, WA

T: 541.741.2975 | Cell: 503.869.4885 | Chris.Link@msa-ep.com

777 High Street, Suite 200 | Eugene, Oregon 97401 | www.msa-ep.com

Murray, Smith & Associates, Inc. | Your Public Works Partner

Notice: This e-mail and any attached files are the private confidential property of the sender, and the materials are privileged communications intended solely for the receipt, use, benefit and information of the intended recipient indicated above. If you are not the intended recipient, you are hereby notified that any review, disclosure, copying, distribution, or taking of any other action in reliance on the contents of this transmission is strictly prohibited, and may result in legal liability on your part. If you have received this e-mail in error, please notify us immediately at the above address.

P Please consider the environment before printing this e-mail.

From: Evan Goepferd [mailto:evan@weitmanexcavation.com]

Sent: Tuesday, January 12, 2016 3:26 PM

To: Chris Link <Chris.Link@msa-ep.com>

Subject: Projects Bidding:// City of Molalla - Molalla Avenue Improvements – Urban Renewal

City of Molalla - Molalla Avenue Improvements – Urban Renewal

I found this project on Oregon Bid Network and have downloaded the Plans and Specs off of the Contractor Plan Center as of 3:00PM today, 12-JAN-2016. The description states to contact Chris Link within 24 Hours of downloading the documents.

Please write back to confirm you have received the email and to provide me with any further direction as necessary.

Project Name: Molalla Avenue Improvements – Urban Renewal

Owner: City of Molalla

Project Location: Molalla, OR

Bid Due Date: 27-JAN-2016 [Wednesday]

EE: $2MM to $2.5MM

Bid Bond: 5%

Completion Date: 30-NOV-2016

Thank you.

Evan Goepferd

Estimator / Project Manager

Weitman Excavation, LLC

Office: 11225 SW Clay Street, Sherwood, OR 97140

Cell: 503.452.2539 • Work: 503.682.3322 • Fax: 503.682.3366

www.weitmanexcavation.com