From: Jennifer Cline

Sent: Tue Dec 23 10:56:34 2014

To: Garrett Edmunds

Subject: RE: Paving

Importance: Normal

 

Hi Garrett,

He can pave if the following conditions can be met:

· A pre-paving meeting must be scheduled in advance and includes the contractor(himself), paving sub, testers and the City reps.

· The city needs to verify the mix design meets the Level 2, PG 64-22 - ½” Dense HMAC requirements (as stated on the plans), I need the JMF at least 24 hours in advance of the pre-paving meeting.

· Temperature must be 40 degrees minimum and rising measured on the rock/ground

· No standing water is allowed (puddles)

Also, ask him if he knows the tonnage to be placed to determine if the work can qualify under minor HMAC. I’m assuming not, but wanted to clarify.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Garrett Edmunds [mailto:gedmunds@cityofmolalla.com]

Sent: Tuesday, December 23, 2014 10:17 AM

To: Jennifer Cline

Subject: Paving

Hello,

I spoke with Scott Hewitt this morning about paving on 12-29 or 12-30. The weather repot says clear and cold 41/21. If it is that cold shall we tell them to hold off?

Thanks

Garrett Edmunds

Operation Division Supervisor

117 N Molalla Ave PO Box 248

Molalla, OR 97038

503-829-5401

503-829-3676(fax)

gedmunds@cityofmolalla.com