From: Jennifer Cline
Sent: Tue Jan 13 13:20:56 2015
To: Scott Hewett
Cc: Garrett Edmunds
Subject: RE: paving
Importance: Normal
Hi Scott,
I will send you a letter on letterhead later today. I’ve been in meetings mostly all morning and have not had a chance to write it up yet.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Scott Hewett [mailto:scott.hewett23@gmail.com]
Sent: Tuesday, January 13, 2015 12:47 PM
To: Jennifer Cline
Subject: Re: paving
Hi
I wanted to see if you came up with a list on the paving issues or have you been in contact with Dave. I need to get something going with him to correct.
Thank you
Scott Hewett, President
Hewett Construction
PH: 971-246-0501
F: 503-628-1386
On Jan 8, 2015, at 5:39 PM, Jennifer Cline <jcline@cityofmolalla.com> wrote:
Hi Scott,
Garrett expressed concern today regarding the paving quality. The compaction appeared to be good, but today I see some other quality issues so I’m having the Oregon City paving inspector come out next week if available. We will be looking at the quality of the joints, transitions and over mix placement to get his input. In addition we saw some unraveling at the joints and voids in the mat.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676