From: Jennifer Cline

Sent: Wed May 06 18:55:26 2015

To: Curtis Cooksey

Cc: hai@curran-mcleod.com; Dan Huff

Subject: RE: Over-ex/Dig-outs Measurements

Importance: Normal

 

Hi Curtis,

In regards to Article 13.03-E.1 of The Standard General condition of The Construction Contract, the City is requesting to seek an adjustment in unit price for Bid Item A.6 to account the increase in quantities of 94%, from 50 CY to 811.4 CY. Please provide with justification.

Regards,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Tuesday, May 05, 2015 10:42 AM

To: Jennifer Cline

Cc: hai@curran-mcleod.com

Subject: RE: Over-ex/Dig-outs Measurements

Hi Jennifer,

I’m sending you the locations and areas of the subgrade stabilization.

Let me know if you have any questions.

Curtis

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Tuesday, April 28, 2015 9:23 AM

To: Curtis Cooksey

Cc: Hassan Ibrahim; Dan Huff

Subject: Over-ex/Dig-outs Measurements

Hi Curtis,

We have had several dig-outs on this project for subgrade stabilization as you are aware. I would like to verify Barbs notes/spreadsheet to confirm measurement areas for payment. I’m assuming the measurements were also done for the few dig-outs on Grange and Heintz as well by Walter?

Thank you,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C: