From: Jennifer Cline
Sent: Wed May 06 18:55:26 2015
To: Curtis Cooksey
Cc: hai@curran-mcleod.com; Dan Huff
Subject: RE: Over-ex/Dig-outs Measurements
Importance: Normal
Hi Curtis,
In regards to Article 13.03-E.1 of The Standard General condition of The Construction Contract, the City is requesting to seek an adjustment in unit price for Bid Item A.6 to account the increase in quantities of 94%, from 50 CY to 811.4 CY. Please provide with justification.
Regards,
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]
Sent: Tuesday, May 05, 2015 10:42 AM
To: Jennifer Cline
Cc: hai@curran-mcleod.com
Subject: RE: Over-ex/Dig-outs Measurements
Hi Jennifer,
I’m sending you the locations and areas of the subgrade stabilization.
Let me know if you have any questions.
Curtis
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Tuesday, April 28, 2015 9:23 AM
To: Curtis Cooksey
Cc: Hassan Ibrahim; Dan Huff
Subject: Over-ex/Dig-outs Measurements
Hi Curtis,
We have had several dig-outs on this project for subgrade stabilization as you are aware. I would like to verify Barbs notes/spreadsheet to confirm measurement areas for payment. I’m assuming the measurements were also done for the few dig-outs on Grange and Heintz as well by Walter?
Thank you,
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676