From: Jennifer Cline
Sent: Wed May 06 19:02:14 2015
To: hai@curran-mcleod.com
Subject: RE: Over-ex/Dig-outs Measurements
Importance: Normal
Hi Hassan, Do you have a suggested fair cost for the work? They used 3” minus or ¾” minus for the backfill, plus the cost of 1 operator, 1 laborer and 2-3 trucks with drivers including haul each day (they were hauling to Canby). The geotextile should be paid under the agreed cost Curtis gave us awhile back.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]
Sent: Wednesday, May 06, 2015 6:01 AM
To: 'Jennifer Cline'
Cc: 'Dan Huff'
Subject: RE: Over-ex/Dig-outs Measurements
Yes, it does under Article 13.03-E.1 of “The Standard General Conditions of The Construction Contract”.
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Tuesday, May 05, 2015 4:36 PM
Cc: Dan Huff
Subject: RE: Over-ex/Dig-outs Measurements
My only question is that we went from 50 cy to 811.4 cy. This exceeds the original bid cost significantly. Does the city have the right to request a credit due the 94% increase in quantity.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]
Sent: Tuesday, May 05, 2015 2:46 PM
To: 'Jennifer Cline'
Subject: FW: Over-ex/Dig-outs Measurements
Hi Jen,
EE are showing 811.4 CY of over excavation @ $88.00/CY totaling $71,403.20?
What are your thoughts?
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com
From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]
Sent: Tuesday, May 05, 2015 10:42 AM
To: Jennifer Cline
Subject: RE: Over-ex/Dig-outs Measurements
Hi Jennifer,
I’m sending you the locations and areas of the subgrade stabilization.
Let me know if you have any questions.
Curtis
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Tuesday, April 28, 2015 9:23 AM
To: Curtis Cooksey
Cc: Hassan Ibrahim; Dan Huff
Subject: Over-ex/Dig-outs Measurements
Hi Curtis,
We have had several dig-outs on this project for subgrade stabilization as you are aware. I would like to verify Barbs notes/spreadsheet to confirm measurement areas for payment. I’m assuming the measurements were also done for the few dig-outs on Grange and Heintz as well by Walter?
Thank you,
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676