From: Jennifer Cline

Sent: Tue May 12 18:15:53 2015

To: Hassan Ibrahim

Cc: Dan Huff; Heather Penni

Subject: RE: Over-ex/Dig-outs Measurements

Importance: Normal

Attachments: Eagle_Elsner001.pdf; Eagle_Elsner006.pdf; image001.png;

 

Hassan, Do you agree with this unit cost? If feel like this is extremely high compared to other contractor bids we have seen.

I have a few questions that need to be verified

· Did they include the crushed surfacing in the quantities, where was the depth measured from is the better question? For example on Stowers the crush surfacing is 1 foot, was any of that 1 included in the depth? This can be verified by rock tickets quantities for the given days on the estimate. The removal on Heintz falls under the pavement repair cross-section on Sheet C17, Detail 6. And same with the majority of Grange. Only 1” of the 10” can be paid by Over excavation.

· Do the labor hours match the reported hours and wages to Boli (I have not seen but one (1) wage report the entire contract)

· Why is subgrade fabric included if we are paying for it under Bid item B-11

· I don’t see invoices for the rock tickets or dump fees to verify unit cost price.

Thanks,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Tuesday, May 12, 2015 6:18 AM

To: Jennifer Cline

Cc: hai@curran-mcleod.com

Subject: RE: Over-ex/Dig-outs Measurements

Jennifer,

I’m sending you the cost breakdown for the subgrade/ trench stabilization, as you will notice the cost is higher than bid, I just rounded the number down to $88.00 at bid time.

Curtis

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Wednesday, May 06, 2015 6:54 PM

To: Curtis Cooksey

Cc: hai@curran-mcleod.com; Dan Huff

Subject: RE: Over-ex/Dig-outs Measurements

Hi Curtis,

In regards to Article 13.03-E.1 of The Standard General condition of The Construction Contract, the City is requesting to seek an adjustment in unit price for Bid Item A.6 to account the increase in quantities of 94%, from 50 CY to 811.4 CY. Please provide with justification.

Regards,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Tuesday, May 05, 2015 10:42 AM

To: Jennifer Cline

Cc: hai@curran-mcleod.com

Subject: RE: Over-ex/Dig-outs Measurements

Hi Jennifer,

I’m sending you the locations and areas of the subgrade stabilization.

Let me know if you have any questions.

Curtis

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Tuesday, April 28, 2015 9:23 AM

To: Curtis Cooksey

Cc: Hassan Ibrahim; Dan Huff

Subject: Over-ex/Dig-outs Measurements

Hi Curtis,

We have had several dig-outs on this project for subgrade stabilization as you are aware. I would like to verify Barbs notes/spreadsheet to confirm measurement areas for payment. I’m assuming the measurements were also done for the few dig-outs on Grange and Heintz as well by Walter?

Thank you,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image