From: Jennifer Cline
Sent: Fri Mar 20 09:29:35 2015
To: PEIRCE Nicole M
Subject: RE: OR 213 Paving from Mulino to Blackmans Corner
Importance: Normal
Thank you, I appreciate your help.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: PEIRCE Nicole M [mailto:Nicole.M.PEIRCE@odot.state.or.us]
Sent: Thursday, March 19, 2015 9:07 AM
To: 'Jennifer Cline'
Cc: dhuff@cityofmolalla.com; Dennis Welle; ashultz@cityofmolalla.com; MANSELLE Douglas L
Subject: RE: OR 213 Paving from Mulino to Blackmans Corner
Hi Jennifer,
Attached are the current schedule and the plan set. (I had to delete the pages of the plan set that had standard drawings in order to get the file small enough to send via email.) Moving forward, I suggest you coordinate with Doug Manselle in the construction office (503-731-4877 and cc’ed on this email).
Thanks,
Nicole Peirce - Project Leader, ODOT Region 1 ( 503-731-3289
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Wednesday, March 18, 2015 11:16 AM
To: PEIRCE Nicole M
Cc: dhuff@cityofmolalla.com; Dennis Welle; ashultz@cityofmolalla.com
Subject: RE: OR 213 Paving from Mulino to Blackmans Corner
Hi Nicole,
The City had noticed the contractor doing some work on OR 213, which I assume is the start of the Paving project from Mulino to Blackman’s Corner. I have a couple of requests for you if you are the correct contact.
· Can I get a copy of the plan set
· Can I also get a copy of the contractors schedule, we are looking to place two water services in a single trench across OR213 for the properties at Stutz Auto Body Shop, 31459 OR-213, Molalla & Sawyers Truck Repair, 31361 OR-213 Molalla. The trench will cross at the property line between the two. My main concern is that we get this work done prior to your paving schedule and coordinate with the contractors traffic control.
Please feel free to give me a call if you have any questions.
Regards,
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: WATANABE Richard F [mailto:Richard.F.WATANABE@odot.state.or.us]
Sent: Friday, March 13, 2015 8:26 AM
To: 'Jennifer Cline'; PEIRCE Nicole M
Cc: dhuff@cityofmolalla.com; BROOKS Kelly S; MILLER Theodore C
Subject: RE: OR 213 Paving from Mulino to Blackmans Corner
Jennifer,
Our Project Leader is Nicole Peirce and I am copying her on this list. Her number is 503-731-8289.
Thanks
Rich
Rich Watanabe, P.E.
Metro East Area Manager, Region 1
Oregon Department of Transportation
123 NW Flanders St.
Portland, OR 97209
Voice: (503)731-8528
Fax: (503)731-8531
From: BROOKS Kelly S
Sent: Thursday, March 12, 2015 4:10 PM
To: MILLER Theodore C; WATANABE Richard F
Cc: dhuff@cityofmolalla.com; 'Jennifer Cline'
Subject: RE: OR 213 Paving from Mulino to Blackmans Corner
Jennifer,
I don’t recall but Ted or Rich would likely know so I’ve sent it their way.
Kelly Scannell Brooks
Interim Policy and Development Manager
ODOT Region 1
(503) 731-3087 (Flanders)
(503) 725-2186 (Metro RSC)
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Thursday, March 12, 2015 4:08 PM
To: BROOKS Kelly S
Cc: dhuff@cityofmolalla.com; WATANABE Richard F
Subject: OR 213 Paving from Mulino to Blackmans Corner
Hi Kelly,
Can you please pass on the Design Project Manager contact information for the Mulino to Blackman’s Corner paving project? I wrote it down but do not have it now. I have a few question regarding the upcoming project and possibly coordinating some waterline work prior to paving the top lift.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676