Hi Nicole,

The City had noticed the contractor doing some work on OR 213, which I assume is the start of the Paving project from Mulino to Blackman’s Corner. I have a couple of requests for you if you are the correct contact.

· Can I get a copy of the plan set

· Can I also get a copy of the contractors schedule, we are looking to place two water services in a single trench across OR213 for the properties at Stutz Auto Body Shop, 31459 OR-213, Molalla & Sawyers Truck Repair, 31361 OR-213 Molalla. The trench will cross at the property line between the two. My main concern is that we get this work done prior to your paving schedule and coordinate with the contractors traffic control.

Please feel free to give me a call if you have any questions.

Regards,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: WATANABE Richard F [mailto:Richard.F.WATANABE@odot.state.or.us]

Sent: Friday, March 13, 2015 8:26 AM

To: 'Jennifer Cline'; PEIRCE Nicole M

Cc: dhuff@cityofmolalla.com; BROOKS Kelly S; MILLER Theodore C

Subject: RE: OR 213 Paving from Mulino to Blackmans Corner

Jennifer,

Our Project Leader is Nicole Peirce and I am copying her on this list. Her number is 503-731-8289.

Thanks

Rich

Rich Watanabe, P.E.

Metro East Area Manager, Region 1

Oregon Department of Transportation

123 NW Flanders St.

Portland, OR 97209

Voice: (503)731-8528

Fax: (503)731-8531

From: BROOKS Kelly S

Sent: Thursday, March 12, 2015 4:10 PM

To: MILLER Theodore C; WATANABE Richard F

Cc: dhuff@cityofmolalla.com; 'Jennifer Cline'

Subject: RE: OR 213 Paving from Mulino to Blackmans Corner

Jennifer,

I don’t recall but Ted or Rich would likely know so I’ve sent it their way.

Kelly Scannell Brooks

Interim Policy and Development Manager

ODOT Region 1

(503) 731-3087 (Flanders)

(503) 725-2186 (Metro RSC)

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Thursday, March 12, 2015 4:08 PM

To: BROOKS Kelly S

Cc: dhuff@cityofmolalla.com; WATANABE Richard F

Subject: OR 213 Paving from Mulino to Blackmans Corner

Hi Kelly,

Can you please pass on the Design Project Manager contact information for the Mulino to Blackman’s Corner paving project? I wrote it down but do not have it now. I have a few question regarding the upcoming project and possibly coordinating some waterline work prior to paving the top lift.

Jennifer Cline, P.E.