From: Jennifer Cline

Sent: Thu Mar 26 10:21:57 2015

To: jake ehredt

Cc: Jason Clifford

Subject: RE: new big gun

Importance: Normal

Attachments: image002.png;

 

Ok, I will be preparing an agenda item or April council meeting on the 15th I believe. I will let you know once we have approve to place the order.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image

From: jake ehredt [mailto:jehredt@cityofmolalla.com]

Sent: Thursday, March 26, 2015 10:20 AM

To: Jennifer Cline

Subject: new big gun

Jen,

I spoke with Leo from Valley Fab and he said that if we want to get the big gun in June that will not be a problem. I told him that we would make payment in July

Jake Ehredt

City of Molalla

Asst. Wastewater Plant Operator

12424 S. Toliver rd

Molalla Or, 97038

Wwtp (503)829-5407

Cell 971-241-7547