From: Jennifer Cline
Sent: Wed May 06 16:35:03 2015
To: STRULOEFF Michael R
Subject: RE: Mulino -Blackman Corner-construction staging is not permitted with in the City ROW
Importance: Normal
Hi Mike,
Thank you for the response, I think Doug Manselle may have already notified Kerr.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: STRULOEFF Michael R [mailto:Michael.R.STRULOEFF@odot.state.or.us]
Sent: Wednesday, May 06, 2015 10:00 AM
To: 'Jennifer Cline'
Cc: MANSELLE Douglas L; MADORIN Helen; Nicolas Lennartz; Dan Huff; 'Brandon Adams'; GWARTNEY Randy
Subject: RE: Mulino -Blackman Corner-construction staging is not permitted with in the City ROW
I will pass this along to Kerr-thanks for the e-mail
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Tuesday, May 05, 2015 8:45 AM
To: STRULOEFF Michael R
Cc: MANSELLE Douglas L; MADORIN Helen; Nicolas Lennartz; Dan Huff
Subject: RE: Mulino -Blackman Corner-phone list-3 week schedule-project schedule
Hi Mike,
Yesterday we noticed Kerr is staging several pieces of equipment within the City limits on Industrial Way, just off Toliver Rd. While the equipment on the private property is permitted with the owner’s consent, the equipment (rollers) parked on Industrial Way is not. In addition, there are posted signs limiting parking to 3 hours. Will you please pass the message along to Kerr contractors?
Please note, construction staging is not permitted with in the City ROW without the proper construction permit or under contract with the City of Molalla.
Thank you,
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: STRULOEFF Michael R [mailto:Michael.R.STRULOEFF@odot.state.or.us]
Sent: Thursday, March 19, 2015 9:34 AM
To: 'jcline@cityofmolalla.com'
Cc: MANSELLE Douglas L; MADORIN Helen
Subject: Mulino -Blackman Corner-phone list-3 week schedule-project schedule
ODOT Ast.PM Mike -503-731-45237
ODOT PC Doug 503-731-4877
ODOT Inspector Helen 503-969-1056
Above are the phone numbers for ODOT and Kerr contractor field people for this project , project schedule and 3 week look ahead schedule .
Rich Watanabe called and asked me to give you a call.
I also called you today and left you a message.