From: Jennifer Cline
Sent: Sat Oct 18 09:39:28 2014
To: David Little
Cc: Garrett Edmunds
Subject: Re: Mountain View Lane
Importance: Normal
Hi David,
We are waiting on the availability of contractor to complete the patch work. Paving contractors are extremely busy this time of year trying to beat the whether. After speaking with the contractor we are about 2-3 weeks out until they are available, whether permitting.
Regards,
Jenn Cline
Sent from my iPhone
On Oct 17, 2014, at 9:44 AM, David Little <davestuff@molalla.net> wrote:
Hi Jennifer,
I am writing to inquire as to the repair schedule on Mountain View Lane. Crews dug up the road to fix a water leak and never finished it. It has just been gravel for over a month now. When do you foresee this being finished?
Dave and Mary Little
1318 Mountain View Lane