Attached is the invoice detailing the equipment purchased. I’ve asked Correct Equipment to provide the specifications, however here is a link to the manufactures specs. The application states this flow meter is for water or wastewater pipes.

https://www.pulsar-pm.com/product-types/flow/flow-pulse.aspx

Let me know if you have any other questions,

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Gerald Fisher [mailto:geraldf@pdgnw.com]

Sent: Friday, June 17, 2016 3:04 PM

To: R Quigley <rquigley@dyerpart.com>

Cc: Jason Clifford <jclifford@cityofmolalla.com>; Jennifer Cline <jcline@cityofmolalla.com>

Subject: RE: Molalla WWTP

Yep.

Jason, please confirm with Ryan the question below. Thanks.

Gerald

Sent from my Verizon Wireless 4G LTE smartphone

 

 

-------- Original message --------

From: R Quigley <rquigley@dyerpart.com>

Date: 06/17/2016 2:54 PM (GMT-08:00)

To: Gerald Fisher <geraldf@pdgnw.com>

Subject: RE: Molalla WWTP

Gerald,

As you saw, I mentioned to Randy that I assume the ultrasonic meter the City is looking at is acceptable for wastewater. Can we confirm?

Thanks,

Ryan

From: Gerald Fisher [mailto:geraldf@pdgnw.com]

Sent: Friday, June 17, 2016 2:00 PM

To: R Quigley

Cc: Gerald Fisher

Subject: RE: Molalla WWTP

Sounds good Ryan

From: R Quigley [mailto:rquigley@dyerpart.com]

Sent: Friday, June 17, 2016 1:33 PM

To: Gerald Fisher <geraldf@pdgnw.com>

Cc: Gerald Fisher <gfisher@cityofmolalla.com>

Subject: RE: Molalla WWTP

Gerald,

I was talking schedule with Steve yesterday and if the meter gets installed in the next week or two, we will plan on starting the test run the week of July 11th. Steve is available the 12th or 15th to make a trip up here to help me things started. Just wanted to give you a heads up on what we are thinking schedule wise. If you have any thoughts or concerns, just let me know.

Thanks,

Ryan

From: Gerald Fisher [mailto:geraldf@pdgnw.com]

Sent: Wednesday, June 15, 2016 2:22 PM

To: R Quigley

Subject: RE: Molalla WWTP

Thanks Ryan

Sent from my Verizon Wireless 4G LTE smartphone

 

 

-------- Original message --------

From: R Quigley <rquigley@dyerpart.com>

Date: 06/15/2016 1:55 PM (GMT-08:00)

To: Gerald Fisher <geraldf@pdgnw.com>

Cc: S Major <smajor@dyerpart.com>

Subject: Molalla WWTP

Gerald,

See attached for changes we discussed. Both the memo and Fig B have been revised to show the effluent flow meter as future. Please take a look and let me know if you see any issues or have any questions. Please forward to the City and DEQ if it looks acceptable.

Thanks,

Ryan Quigley, P.E.

The Dyer Partnership

Engineers & Planners, Inc.

1165 S. Park St.

Lebanon, OR 97355

(541) 405-4520 – Office

(541) 451-0089 – Cell

rquigley@dyerpart.com

www.dyerpart.com


 

No virus found in this message.

Checked by AVG - www.avg.com

Version: 2016.0.7640 / Virus Database: 4604/12427 - Release Date: 06/15/16


 

No virus found in this message.

Checked by AVG - www.avg.com

Version: 2016.0.7640 / Virus Database: 4604/12438 - Release Date: 06/17/16