From: Jennifer Cline

Sent: Tue May 12 10:06:06 2015

To: Dave Scott

Cc: Dan Zinder; Dennis Welle

Subject: RE: Molalla Sewer & Storm CCTV quote request

Importance: Normal

Attachments: Molalla Avenue Exhibits - 20 Scale.pdf;

 

Hi Dave,

Here is the updated survey information I spoke about on the phone. We will be sending you the Manhole ID’s shortly for the storm and sewer manholes.

Regards,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image

From: Dave Scott [mailto:dscott@tvmypipe.com]

Sent: Friday, May 08, 2015 2:17 PM

To: Jennifer Cline

Subject: Re: Molalla Sewer & Storm CCTV quote request

Hi Jennifer -

Attached is a quote for the TV work you requested.

 

Let me know if you want to proceed and we can talk schedule.

 

Thanks.

 

 

Dave Scott

 

Pacific Int-R-Tek

 

2501 NW Division St. Gresham, OR 97030

 

Office 503-665-1090 Cell 503-730-4343

 

Providing Pipeline Video Service

 

OR CCB #146869, WA PACIFI*991CW

 

 

On 5/7/2015 5:08 PM, Jennifer Cline wrote:

Hi Dave, We are only looking to CCTV Molalla Ave between 5th St and Shirley Ave, which the engineer est 5000 LF total for both. Yes, TV only no electronic locates.

Yes, this is part of pre engineering study.

I will have our crew flush the lines prior to the work. Go ahead and include TTC in your bid as well.

Regards,

JC

 

Sent from my iPhone

 

On May 7, 2015, at 3:54 PM, Dave Scott <dscott@tvmypipe.com> wrote:

Jennifer -

Thanks. I got it.

I just want to do a few quick fact checks.

 

On a quick review it looks like there is roughly 5,000' of Storm and 5,000' of Sanitary pipe. Does that sound right?

Also it looks like all the sanitary is 8" and storm mains are all 12" with a little 10" maybe. I assume you want to run all the pipe in the project areas - Sanitary mains, Storm mains and Storm Catch basin inlets. Assume sanitary laterals would not be included. Assume lines would be televised only, no electronic locates are required.

 

I'm assuming this is not part of the Urban Renewal project and not prevailing wage. It is preliminary study for engineer prior to the project for design.

 

I would assume that the city would clean the lines ahead as needed, and vac truck would be available for additional cleaning if needed.

 

It looks like formal traffic control / flaggers would be minimal, we would plan to bring in flaggers as needed and invoice at costs plus 10% or City could provide flagging if so desired.

 

If that all looks good, I can work up a quote for.

Thanks.

 

 

 

 

 

 

Dave Scott

 

Pacific Int-R-Tek

 

2501 NW Division St. Gresham, OR 97030

 

Office 503-665-1090 Cell 503-730-4343

 

Providing Pipeline Video Service

 

OR CCB #146869, WA PACIFI*991CW

 

 

On 5/7/2015 3:00 PM, Jennifer Cline wrote:

Hi Dave,

Attached is the map along with the kmz files. The engineers estimate close to 5000 LF of total sewer and storm mains that they would like video and notes on.

We are looking to have the final report completed in 7-10 business days.

I look forward to your quote and let me know if you have any questions.

Regards,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image