From: Jennifer Cline

Sent: Tue Apr 14 13:38:42 2015

To: Lee, Rob

Subject: RE: Molalla Modeling

Importance: Normal

Attachments: image001.gif;

 

Hi Rob,

Thank you, I will talk with Dan further about beginning this work this year. He’s hesitant to spend money still, however I do have I&I funds still available.

Regards,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Lee, Rob [mailto:roblee@BrwnCald.com]

Sent: Tuesday, April 14, 2015 12:02 PM

To: Jennifer Cline

Subject: RE: Molalla Modeling

Jennifer,

Just the modeling would be ~$30,800. The memo should be fairly straightforward and simple, so we didn’t allocate a lot of budget for putting it together.

Robert Lee

Brown and Caldwell

roblee@brwncald.com

T 503.977.6625 | C 503.828.7542

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Monday, April 13, 2015 5:40 PM

To: Lee, Rob

Subject: RE: Molalla Modeling

Hi Rob,

Can you give me a total cost just to do the modeling?

Thank you,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Lee, Rob [mailto:roblee@BrwnCald.com]

Sent: Monday, April 13, 2015 2:46 PM

To: Jennifer Cline

Subject: Molalla Modeling

Jennifer,

I just checked and you are correct, we deferred the modeling until the next fiscal year. The estimate for putting together the model and a simple memo highlighting the modeling results (both current and future capacity issues) is $34,500. The money saved by not performing the WWTF evaluation is $26,800.

Let me know if you’d like for us to get started on putting the model together. We’d be happy to but we could also wait until the City’s next fiscal year.

In the meantime, based on the flow monitoring results, I’ll work with Rylee here to start putting together an initial plan for CCTV and smoke-testing.

Robert Lee, P.E.

Brown and Caldwell

roblee@brwncald.com

T 503.977.6625 | C 503.828.7542

 

image