From: Jennifer Cline

Sent: Fri Aug 07 08:32:16 2015

To: COLE David

Cc: Jason Clifford

Bcc: Christine Hein; Mark Strandberg

Subject: Re: Molalla lagoon leak test.

Importance: Normal

 

David,

 

We have the leak test prepped & scheduled to start next week. However, rain is in the upcoming forecast and it may be delayed. Please note I am out of the office and will be returning on Monday.

 

Regards,

Jenn Cline

 

Sent from my iPhone

 

On Aug 5, 2015, at 2:25 PM, COLE David <COLE.David@deq.state.or.us> wrote:

 

Hi Jennifer. Just a reminder/check-in to see how your plans are shaping up for the lagoon leak test that the permit requires (Sch. D, condition 14).

David Cole, R.G.

Water Quality Specialist

DEQ Northwest Region & Western Region

700 NE Multnomah St., Suite 600

Portland, OR 97232

(T) 503-229-5011

(F) 503-229-6957

cole.david@deq.state.or.us