From: Jennifer Cline

Sent: Wed Nov 05 15:56:30 2014

To: J.W. Ring

Cc: Dan Huff

Subject: RE: Molalla issues

Importance: Normal

Attachments: RE: Molalla issues; image001.jpg; City of Molalla NPDES Permit and I& I Progress; RE: City of Molalla NPDES Permit and I& I Progress; image002.png;

 

Hi Jeff,

I would like to confirm the final date of submittal for the Inflow Removal Plan. As written in Schedule D, Section 1(a) of the NPDES Permit # 101514, the Inflow Removal Program must be submitted for approval within 180 days of the effective date. We understood that conditional approval was given to the City on July 29th, 2014 and not 5.12.14 as mentioned in the attached email chain to miss Hanson.

In the email from Mark he indicated the effective date was June 1st, which still would have given us until the end of November. I had also requested a examples on Sept. 25th to help us through the development process, which I have not received.

Sincerely,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

From: Dan Huff [mailto:dhuff@cityofmolalla.com]

Sent: Wednesday, November 05, 2014 3:16 PM

To: Jennifer Cline

Subject: FW: Molalla issues

FYI

From: J.W. Ring [mailto:JWRing@ringbenderlaw.com]

Sent: Wednesday, November 05, 2014 3:01 PM

To: Dan Huff

Subject: RE: Molalla issues

Thank you for remaining calm, I will check on this and get back to you.

From: Dan Huff [mailto:dhuff@cityofmolalla.com]

Sent: Wednesday, November 05, 2014 2:57 PM

To: J.W. Ring

Subject: RE: Molalla issues

O.K. We have been plugging away on our I&I plan based on a January due date so let me know where we go at this point and I will remain calm.

From: J.W. Ring [mailto:JWRing@ringbenderlaw.com]

Sent: Wednesday, November 05, 2014 2:42 PM

To: Dan Huff; Phillip Bender; Mark Strandberg

Subject: RE: Molalla issues

Remain calm, the meeting today with DEQ re depositions went well. They are working with us. We will address this issue with them.

Jeff

J.W. Ring

Managing Partner

image

Ring, Bender, McKown & Castillo

[T] (503) 964-6723 office direct

[T] (503) 841-9380 mobile one

[T] (503) 841-8415 mobile two

email: jwring@ringbenderlaw.com

This transmission is intended for the sole use of the individual or entity to whom it is addressed, and may contain information that is privileged, confidential and exempt from disclosure under applicable law. You are hereby notified that any dissemination, distribution or duplication of this transmission by someone other than the intended addressee or its designated agent is strictly prohibited. If your receipt of this transmission is in error, please notify this firm immediately by telephone at (503) 964-6730, or reply to this transmission. Thank you. Ring, Bender, McKown & Castillo: Portland, Or. - Orange County, Ca. - Miami, Fl. - Pittsburgh, Pa. - Seattle, Wa. – Phoenix, Az.

From: Dan Huff [mailto:dhuff@cityofmolalla.com]

Sent: Wednesday, November 05, 2014 2:34 PM

To: J.W. Ring; Phillip Bender; Mark Strandberg

Subject: FW: Molalla issues

Jeff, et al – My concern regarding tiffany Yelton –Brands e-mail is that we did not receive conditional approval from DEQ until July 29, 2014. Also, I find it offensive that DEQ is cow towing to Ms. Hansen.

Dan Huff

City Manager

City of Molalla, Oregon

(503) 829-6855

dhuff@cityofmolalla.com

image

_______________________________________________________________________________

PUBLIC RECORDS LAW DISCLOSURE

This e-mail is a public record of the City of Molalla and is subject to public disclosure unless exempt from disclosure under Oregon Public Records Law. This e-mail is subject to State Retention Schedule

From: YELTON-BRAM Tiffany [mailto:YELTON-Bram.Tiffany@deq.state.or.us]

Sent: Wednesday, November 05, 2014 12:41 PM

To: 'Jennifer Cline'

Cc: Phillip Bender; Garrett Edmunds; Dan Huff; COLE David

Subject: RE: Molalla issues

Thank you for the reply. Nina Deconcini is out currently and I am not seeing much opportunity on her calendar for an afternoon meeting or cal on the 19th or 20th. If 10am on the 19th isn’t possible for a half hour call, then I will need to seek a date and time the following week.

Most immediately, I do hope that you’ll be in touch before the 11th of this month to let us know (David Cole and myself) that the Inflow Removal Plan is complete. Thanks!

Tiffany Yelton Bram

Water Quality Source Control Section Manager

Water Quality Program, NW Region

Oregon Department of Environmental Quality

2020 SW 4th Ave., Suite 150

Portland OR 97201-4987

desk 503 229 5219

mobile 503 975 0046

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Monday, November 03, 2014 9:27 AM

To: YELTON-BRAM Tiffany

Cc: Phillip Bender; Garrett Edmunds; Dan Huff

Subject: Re: Molalla issues

Hi Tiffany,

We have been busy wrapping up City projects and along preparing to deliver a large street project for advertisement. As these projects are coming to an end, I am beginning to work on the I & I removal plan along with developing a revised TMDL. The week before last we finished mapping the entire system. I am excited to begin moving forward with the next step of identifying critical areas needing repairs or replacement.

As for a meeting time, November the 19th or 20th in the afternoon work best for our team schedule. Please confirm what if this will work for you.

Regards,

Jenn Cline

 

Sent from my iPhone

 

On Oct 31, 2014, at 4:46 PM, YELTON-BRAM Tiffany <YELTON-Bram.Tiffany@deq.state.or.us> wrote:

Hello Jennifer

I wanted to remind you of the due date for the Inflow Removal Plan as described in the city’s NPDES permit. I would appreciate an update on this next week.

I would still like to have a meeting with you and our permit writer, David Cole, to walk through the permit. Nina Deconcini, our regional administrator would also like to attend. David and I could go out your office and bring Nina in by phone. Would 10am on Wednesday, November 19th work for you?

Thanks!

Tiffany Yelton Bram

Water Quality Source Control Section Manager

Water Quality Program, NW Region

Oregon Department of Environmental Quality

2020 SW 4th Ave., Suite 150

Portland OR 97201-4987

desk 503 229 5219

mobile 503 975 0046

From: YELTON-BRAM Tiffany

Sent: Friday, October 31, 2014 4:39 PM

To: 'Susan Hansen'

Cc: DECONCINI Nina; HAMMOND Joni

Subject: RE: Molalla issues

Hello Susan

Regarding the Inflow Removal Plan, the City has a 180 days from the issuance of their permit to create this plan. The permit was issued 5/12/2014 and so the city has to November 11, 2014 to provide the plan.

I spoke on the phone with Jennifer Cline, the new public works director, on October 8th (we could not work out a September 30th meeting) and one of the items we discussed was the progress on creating this plan. The city is working on this but was not yet ready to share a draft.

As of right now, no compliance dates related to Infiltration and Inflow have been missed. I have attached the e-mail that you quoted from, Susan, and a copy of the permit for reference.

Tiffany Yelton Bram

Water Quality Source Control Section Manager

Water Quality Program, NW Region

Oregon Department of Environmental Quality

2020 SW 4th Ave., Suite 150

Portland OR 97201-4987

desk 503 229 5219

mobile 503 975 0046

From: Susan Hansen [mailto:foxglovefarm@inbox.com]

Sent: Thursday, October 30, 2014 2:02 PM

To: YELTON-BRAM Tiffany

Cc: DECONCINI Nina; HAMMOND Joni

Subject: Molalla issues

Dear Tiffany,

 

In reviewing email exchanges we had since early Sept. I have a couple of questions.

 

First, I asked for EPA contacts who oversee the work of Oregon DEQ in relation to wastewater programs for cities like Molalla. You have not provided that info.

 

Second, you indicated you would be following up with Molalla about the progress of their I&I: "During the Spring and Summer of 2014, I had meetings with the city where they stated that a more comprehensive I& I study to determine the overall status of the collection system and associated infrastructure would be created. Section 1 of Schedule D in the NPDES permit issued to Molalla sets a clear requirement that within 180 days of issuing the permit, the city would submit for approval an Inflow Removal Plan. This plan then becomes the benchmark by which annual progress will be measured. I will be following up with the city on Tuesday, September 30th, about the progress on this plan."

 

Did you follow up on Sept 30 and what is the progress?

 

Thanks,

Susan Hansen

Bear Creek Recovery

<mime-attachment>

<Molalla-Final-Permit.pdf>