From: Jennifer Cline

Sent: Wed Mar 23 15:16:15 2016

To: Chris Link

Subject: RE: Molalla Avenue - Pay App Example

Importance: Normal

Attachments: 2016-03-10_Preconstruction Agenda_JC.pdf;

 

See my comments below, the payment process was outlined on the front page of the precon agenda notes.

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Chris Link [mailto:Chris.Link@msa-ep.com]

Sent: Wednesday, March 23, 2016 11:56 AM

To: Jennifer Cline <jcline@cityofmolalla.com>

Cc: Randall Stark <Randall.Stark@msa-ep.com>

Subject: FW: Molalla Avenue - Pay App Example

Jenn – See questions from Sarah below. At the pre-con I believe we discussed an end of month cut-off date for the pay apps (i.e. the pay app would include work through the last day of the month). Does this work for you? Yes

Also, when does the City process the checks and how many days prior does the approved pay app need to be submitted? The Precon Agenda outlined the process. The City will process the checks by the 15th of the following month.

Thanks!

Chris Link, P.E. | Civil Engineer, Associate

Licensed in OR, WA

T: 541.741.2975 | Cell: 503.869.4885 | Chris.Link@msa-ep.com

777 High Street, Suite 200 | Eugene, Oregon 97401 | www.msa-ep.com

Murray, Smith & Associates, Inc. | Your Public Works Partner

Notice: This e-mail and any attached files are the private confidential property of the sender, and the materials are privileged communications intended solely for the receipt, use, benefit and information of the intended recipient indicated above. If you are not the intended recipient, you are hereby notified that any review, disclosure, copying, distribution, or taking of any other action in reliance on the contents of this transmission is strictly prohibited, and may result in legal liability on your part. If you have received this e-mail in error, please notify us immediately at the above address.

P Please consider the environment before printing this e-mail.

From: Sarah Kennedy [mailto:sarah@houckco.com]

Sent: Wednesday, March 23, 2016 11:05 AM

To: Chris Link <Chris.Link@msa-ep.com>

Subject: RE: Molalla Avenue - Pay App Example

Thanks. I see the spreadsheet is set up for the 1st – 31st so I am assuming an end of month cut-off date. What date does it need to be submitted by and what do you anticipate the normal processing time taking from approval to payment?

Sarah Kennedy

M.L. Houck Construction Co

4444 22nd Ave NE, Salem OR 97301

Ph 503-463-7177 fax 503-463-4979

sarah@houckco.com

From: Chris Link [mailto:Chris.Link@msa-ep.com]

Sent: Wednesday, March 23, 2016 10:49 AM

To: Jennifer Cline; 'Sarah Kennedy'; greg@houckco.com

Cc: Daphne Marcyan; Randall Stark

Subject: RE: Molalla Avenue - Pay App Example

Folks – as discussed at the preconstruction meeting, attached is an example of MSA’s application for payment form. Note that a copy of each cover sheet and spreadsheet should be saved each month (usually in pdf and excel format). Let me know if you have any questions, the spreadsheet does tend to get more complicated as the project moves forward, especially if there are quantity changes or change orders.

Chris Link, P.E. | Civil Engineer, Associate

Licensed in OR, WA

T: 541.741.2975 | Cell: 503.869.4885 | Chris.Link@msa-ep.com

777 High Street, Suite 200 | Eugene, Oregon 97401 | www.msa-ep.com

Murray, Smith & Associates, Inc. | Your Public Works Partner

Notice: This e-mail and any attached files are the private confidential property of the sender, and the materials are privileged communications intended solely for the receipt, use, benefit and information of the intended recipient indicated above. If you are not the intended recipient, you are hereby notified that any review, disclosure, copying, distribution, or taking of any other action in reliance on the contents of this transmission is strictly prohibited, and may result in legal liability on your part. If you have received this e-mail in error, please notify us immediately at the above address.

P Please consider the environment before printing this e-mail.

From: Chris Link

Sent: Thursday, March 17, 2016 4:46 PM

To: 'Jennifer Cline' <jcline@cityofmolalla.com>; 'Sarah Kennedy' <sarah@houckco.com>; 'greg@houckco.com' <greg@houckco.com>; 'ken@houckco.com' <ken@houckco.com>; 'mike@houckco.com' <mike@houckco.com>; 'Hash, Kenneth F.' <HashK@hdjdg.com>; 'Sharar, Darlene K.' <ShararD@hdjdg.com>; Randall Stark <Randall.Stark@msa-ep.com>; 'Dan Zinder' <dzinder@cityofmolalla.com>

Cc: Daphne Marcyan <Daphne.Marcyan@msa-ep.com>

Subject: RE: Molalla Avenue - Pre-construction Conference

Folks – PDF versions of the Project Contract Documents, Specifications and Plans with the addenda and signed contract incorporated can be found at the links below. Hard copies will be sent to the City and ML Houck.

Thanks!

Volume 1 – Contract Documents and Specifications https://msaep-my.sharepoint.com/personal/chris_link_msa-ep_com/_layouts/15/guestaccess.aspx?guestaccesstoken=nXEYmlmSekpYwmZds6hMEOxRkhO1d0TSjevce2I7jtg%3d&docid=0a55a4f9fda7f4f139c07040734d23c10

Volume 2 – Plans https://msaep-my.sharepoint.com/personal/chris_link_msa-ep_com/_layouts/15/guestaccess.aspx?guestaccesstoken=rZkoeMJLrOAFE6TVV0yigtLXyx%2bK%2bQnm77z0t0fild4%3d&docid=0c48e0380fb1f40d69c9313f592d8a260

Chris Link, P.E. | Civil Engineer, Associate

Licensed in OR, WA

T: 541.741.2975 | Cell: 503.869.4885 | Chris.Link@msa-ep.com

777 High Street, Suite 200 | Eugene, Oregon 97401 | www.msa-ep.com

Murray, Smith & Associates, Inc. | Your Public Works Partner

Notice: This e-mail and any attached files are the private confidential property of the sender, and the materials are privileged communications intended solely for the receipt, use, benefit and information of the intended recipient indicated above. If you are not the intended recipient, you are hereby notified that any review, disclosure, copying, distribution, or taking of any other action in reliance on the contents of this transmission is strictly prohibited, and may result in legal liability on your part. If you have received this e-mail in error, please notify us immediately at the above address.

P Please consider the environment before printing this e-mail.

From: Chris Link

Sent: Thursday, March 17, 2016 3:26 PM

To: 'Jennifer Cline' <jcline@cityofmolalla.com>; 'Sarah Kennedy' <sarah@houckco.com>; 'greg@houckco.com' <greg@houckco.com>; 'ken@houckco.com' <ken@houckco.com>; 'mike@houckco.com' <mike@houckco.com>; Hash, Kenneth F. <HashK@hdjdg.com>; Sharar, Darlene K. <ShararD@hdjdg.com>; Randall Stark <Randall.Stark@msa-ep.com>; Dan Zinder <dzinder@cityofmolalla.com>

Cc: Daphne Marcyan <Daphne.Marcyan@msa-ep.com>

Subject: Molalla Avenue - Pre-construction Conference

Folks – attached is a summary of action items and additional discussion items from last week’s pre-con. Please review and complete the action items.

I have also attached the subcontractor list and the pre-con sign-in-sheet for your records.

Thanks!

Chris Link, P.E. | Civil Engineer, Associate

Licensed in OR, WA

T: 541.741.2975 | Cell: 503.869.4885 | Chris.Link@msa-ep.com

777 High Street, Suite 200 | Eugene, Oregon 97401 | www.msa-ep.com

Murray, Smith & Associates, Inc. | Your Public Works Partner

Notice: This e-mail and any attached files are the private confidential property of the sender, and the materials are privileged communications intended solely for the receipt, use, benefit and information of the intended recipient indicated above. If you are not the intended recipient, you are hereby notified that any review, disclosure, copying, distribution, or taking of any other action in reliance on the contents of this transmission is strictly prohibited, and may result in legal liability on your part. If you have received this e-mail in error, please notify us immediately at the above address.

P Please consider the environment before printing this e-mail.