From: Jennifer Cline

Sent: Mon Jan 25 15:18:49 2016

To: Chris Link

Cc: dhuff@cityofmolalla.com; dzinder@cityofmolalla.com

Subject: Re: Molalla Ave bid

Importance: Normal

 

If you can't, next Tuesday is ok as well. Just let me know and I will have Dan post the changes when ready.

 

Sent from my iPhone

 

On Jan 25, 2016, at 2:59 PM, Chris Link <Chris.Link@msa-ep.com> wrote:

 

We need to provide 72 hours from when we issue the addendum, so it could be as early as Friday morning or, if we can get it out in the next hour, Thursday at 4:00 PM.

Chris Link, P.E. | Civil Engineer, Associate

Licensed in OR, WA

T: 541.741.2975 | Cell: 503.869.4885 | Chris.Link@msa-ep.com

777 High Street, Suite 200 | Eugene, Oregon 97401 | www.msa-ep.com

Murray, Smith & Associates, Inc. | Your Public Works Partner

Notice: This e-mail and any attached files are the private confidential property of the sender, and the materials are privileged communications intended solely for the receipt, use, benefit and information of the intended recipient indicated above. If you are not the intended recipient, you are hereby notified that any review, disclosure, copying, distribution, or taking of any other action in reliance on the contents of this transmission is strictly prohibited, and may result in legal liability on your part. If you have received this e-mail in error, please notify us immediately at the above address.

P Please consider the environment before printing this e-mail.

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Monday, January 25, 2016 2:53 PM

To: Chris Link <Chris.Link@msa-ep.com>

Cc: dhuff@cityofmolalla.com

Subject: Fwd: Molalla Ave bid

What day do you propose? Next Tuesday?

 

Sent from my iPhone

 

Begin forwarded message:

From: Chris Link <Chris.Link@msa-ep.com>

Date: January 25, 2016 at 2:34:15 PM PST

To: Jennifer Cline <jcline@cityofmolalla.com>

Cc: "Hash, Kenneth F." <HashK@hdjdg.com>

Subject: Molalla Ave bid

Jennifer – we recently received some requirements for the PGE service connections for the street lights. The plans and specs currently have a note for the contractor to coordinate with PGE and install the service connections per their requirements, when available. In order to provide the contractors with a basis to bid on we need to issue addendum #3 showing what those new requirements are (this will give them the information need to bid accurately).

Since we are less than 72 hours from bid, we should push the bid date a few days to allow contractors to address this change. Please give me a call to discuss.

Chris Link, P.E. | Civil Engineer, Associate

Licensed in OR, WA

T: 541.741.2975 | Cell: 503.869.4885 | Chris.Link@msa-ep.com

777 High Street, Suite 200 | Eugene, Oregon 97401 | www.msa-ep.com

Murray, Smith & Associates, Inc. | Your Public Works Partner

Notice: This e-mail and any attached files are the private confidential property of the sender, and the materials are privileged communications intended solely for the receipt, use, benefit and information of the intended recipient indicated above. If you are not the intended recipient, you are hereby notified that any review, disclosure, copying, distribution, or taking of any other action in reliance on the contents of this transmission is strictly prohibited, and may result in legal liability on your part. If you have received this e-mail in error, please notify us immediately at the above address.

P Please consider the environment before printing this e-mail.

<SPDXC65416012515390.pdf>