From: Jennifer Cline
Sent: Thu Oct 08 08:09:34 2015
To: karter@gpecelectric.com
Cc: pjohnson@cityofmolalla.com; dhuff@cityofmolalla.com
Subject: Re: M1677509 - The Lagoon
Importance: Normal
Attachments: image001.jpg; Thanks Karter. We will look for it. JC Sent from my iPhone On Oct 7, 2015, at 8:27 AM, <karter@gpecelectric.com> <karter@gpecelectric.com> wrote: Hi Jennifer, we have started working at the Lagoon. Evidently, PGE needs a signature from the city on their Cost Agreement document. I think Richard is mailing it to you. Thanks Karter From: Richard Mullenburg [mailto:Richard.Mullenburg@pgn.com] Sent: Wednesday, October 07, 2015 8:10 AM Subject: M1677509 - The Lagoon Karter, I am forward over the jobsketch, but has not yet been approved. This means that the inspections cannot be completed till the line extension Cost Agreement has been signed. Thank you, Richard Mullenburg Service and Design Project Manager Portland General Electric Office: (503)-463-6173 <m1677509.pdf>