From: Jennifer Cline

Sent: Tue Jul 28 12:00:03 2015

To: Jason Clifford

Cc: Jake Ehredt

Subject: RE: leak test

Importance: Normal

 

I would like to start August 10th or 11th to give us a 5-day buffer in case any issues pop up with transferring between each lagoon, ect.

Thanks,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Jason Clifford [mailto:jclifford@cityofmolalla.com]

Sent: Tuesday, July 28, 2015 11:49 AM

To: Jennifer Cline <jcline@cityofmolalla.com>

Cc: Jake Ehredt <jehredt@cityofmolalla.com>

Subject: leak test

Hello Jennifer,

We will start lagoon #1 leak test August 15th to the 30th , lagoon #2 August 31st to September 14th and the Aeration Basin September 15th to September 30th.

Thanks,

Jason