From: Jennifer Cline
Sent: Tue Jul 28 12:00:03 2015
To: Jason Clifford
Cc: Jake Ehredt
Subject: RE: leak test
Importance: Normal
I would like to start August 10th or 11th to give us a 5-day buffer in case any issues pop up with transferring between each lagoon, ect.
Thanks,
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Jason Clifford [mailto:jclifford@cityofmolalla.com]
Sent: Tuesday, July 28, 2015 11:49 AM
To: Jennifer Cline <jcline@cityofmolalla.com>
Cc: Jake Ehredt <jehredt@cityofmolalla.com>
Subject: leak test
Hello Jennifer,
We will start lagoon #1 leak test August 15th to the 30th , lagoon #2 August 31st to September 14th and the Aeration Basin September 15th to September 30th.
Thanks,
Jason