From: Jennifer Cline

Sent: Wed Aug 05 12:58:31 2015

To: Jason Clifford

Subject: RE: Lagoon Levels

Importance: Normal

Attachments: image002.png;

 

Thank you for the follow up.

Also, we are a go for the aeration project. I double checked with Dan today. We need to solicit 2 additional quotes on the electrical work for council to approve the work. The next council meeting is on Sept. 23rd. I will need all quotes by Sept. 19th to draft an agenda bill for the packet. I will also need the total costs to purchase the aerator(s) for both lagoons and any additional parts (etc).

You may give a GPEC a heads up in case they want update their quote. I would like to see them do the work.

Here’s a list of electrical contractors in Oregon with their location and specialties listed.

http://electric-contractors.regionaldirectory.us/oregon.htm

Thanks,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

From: Jason Clifford [mailto:jclifford@cityofmolalla.com]

Sent: Wednesday, August 05, 2015 12:24 PM

To: Jennifer Cline <jcline@cityofmolalla.com>

Subject: RE: Lagoon Levels

Hi Jennifer,

We do about an inch a day, give or take. So 12 days for #2 and 24 days for pond #1. We have around ninety days before we’re allowed to discharge, taking into account absolutely no rain until Oct. 31st.

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Wednesday, August 05, 2015 10:32 AM

To: Jason Clifford <jclifford@cityofmolalla.com>

Cc: 'J.W. Ring' <JWRing@ringbenderlaw.com>; 'Christine Hein' <CHein@ringbenderlaw.com>

Subject: Lagoon Levels

Hi Jason,

How many days do we have to hold before we hit 13 feet with the current influent levels.

Regards,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

117 N Molalla Ave.

PO Box 248 *

Molalla, OR 97038

O: 503.759.0218

F: 503.829.3676