From: Jennifer Cline

Sent: Fri May 20 14:01:43 2016

To: Jason Clifford

Subject: RE: Lagoon Levels descriptions

Importance: Normal

 

They are good,

Since you’re including the City notification and RFR contact info, we need to include

· DEQ will be contacted when lagoons reach emergency levels and prior to any unpermitted discharge and

· Operations will prepare to enact the Molalla ERP Spill Response plan in accordance with an unpermitted discharge.

Thanks,

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Jason Clifford [mailto:jclifford@cityofmolalla.com]

Sent: Friday, May 20, 2016 1:17 PM

To: Jennifer Cline <jcline@cityofmolalla.com>

Subject: RE: Lagoon Levels descriptions

Hello Jennifer,

What u think?

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Friday, May 20, 2016 12:32 PM

To: Jason Clifford <jclifford@cityofmolalla.com>

Subject: Lagoon Levels descriptions

Hi Jason,

In the summary I think it would be wise to include the following information on lagoon levels.

Maximum Lagoon Design Capacity: 12-feet

Critical Lagoon Levels: 12 to 13-feet

Emergency Lagoon Levels: Above 13-feet

If we identify this it allows time for the City to make proper notification that if the situations does not subside, the decision will be made to discharge appropriately.

Thanks,

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676