From: Jennifer Cline

Sent: Tue Dec 30 17:18:34 2014

To: Lee, Rob

Cc: Garrett Edmunds

Subject: RE: I/I Flow Meter Location Field Visit

Importance: Normal

Attachments: image001.png;

 

Hi Rob,

I placed the order this afternoon and do our best to collect as much data this year as possible. I’m being optimistic here.

Also, I can move the meeting to Wednesday afternoon. I hope 1 PM will work for both of you? I can be available for lunch at noon if that works also? Just let me know either way.

Regards,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image

From: Lee, Rob [mailto:roblee@BrwnCald.com]

Sent: Tuesday, December 30, 2014 1:55 PM

To: Jennifer Cline

Subject: RE: I/I Flow Meter Location Field Visit

Jennifer,

Got your message. It’s late, but I think if you get the meters and have them in the ground by January 23, we’re likely to get good data through the middle of March. If we don’t get good data, at least you’ll have owned the meters and they can be redeployed next winter.

Also, could we move the location field visit to Wednesday afternoon? The junior engineer I hope to have work on the project, Rylee Archuleta, has a conflict on Tuesday morning. Maybe we could grab lunch and then go look at the sites afterwards on Wednesday the 7th.

Robert Lee

Brown and Caldwell

roblee@brwncald.com

T 503.977.6625 | C 503.828.7542

-----Original Appointment-----

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Monday, December 29, 2014 4:15 PM

To: Lee, Rob; Garrett Edmunds

Subject: I/I Flow Meter Location Field Visit

When: Tuesday, January 06, 2015 10:00 AM-12:00 PM (UTC-08:00) Pacific Time (US & Canada).

Where: Molalla City Hall

Field visit to verify flow meter locations