From: Jennifer Cline

Sent: Tue May 12 08:34:24 2015

To: Curtis Cooksey

Cc: hai@curran-mcleod.com; Dan Huff

Subject: RE: Heintz Street - Digouts & paving

Importance: Normal

Attachments: image002.png;

 

Hi Curtis,

I do understand additional trucks would have been added to remove the additional quantities of the grind. However, that Friday before the pavement work was to begin on Grange and Heintz we reviewed the existing condition of the pavement on both streets with Dick Eagle. It was determined that the majority of both roads needed pavement repair and it would be more cost and time effective to grind it out. I believe the additional pavement repair work would have added significant days to the project and tied your work crews from moving on to other jobs. I was only asking for consideration on this fact.

Thank you,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Tuesday, May 12, 2015 7:23 AM

To: Jennifer Cline

Cc: hai@curran-mcleod.com; Dan Huff

Subject: RE: Heintz Street - Digouts & paving

Hi Jennifer,

The price I sent you was for cost only, I screw up. When you run the numbers it is $3.45 a sy and it was for 0”-2” curb grind that makes it an average of 1” over the 6’ panel.

The City wanted to grind the center of the streets 3” deep an increase of 2”. It cost more to grind 3” also you have an increase in trucking for the extra material removed.

The decision to increase the grind quantity actually added days to the schedule due to the increase in quantity of asphalt material being removed and replaced .

Eagle-Elsner did bid item A-8 Grind Existing Asphalt 6’ wide Panel @ 2” so I can’t delete it, and bid Item B-11 is used to pay for the subgrade fabric that is used on Stowers Road.

Curtis

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Wednesday, May 06, 2015 6:44 PM

To: Curtis Cooksey

Cc: hai@curran-mcleod.com; Dan Huff

Subject: RE: Heintz Street - Digouts & paving

Hi Curtis,

The project was not a complete 3” grind, there was a 2” – 6’ wide grind on the shoulders with and 3” grind on the remaining center of roadway.

Heintz St. – within the project limits shown on Sheets C10-C12,

· 2”- 6’ wide at edge of roadway

· 3” – Varies 24-25’ center of roadway

Grange Ave. – within the project limits shown on Sheets C8-C10,

· 2”- 6’ wide at edge of roadway

· 3” – Varies 30-31’wide center of roadway

I also verified the original S.Y. cost for Bid Item A-8. When you run the numbers it comes to $3.45/s.y. Can you please provide a justification as to why there is an increase of $0.85/s.y. between the two. Typically with an increase in quantities the unit price decreases.

I also ask that you take in account the City’s decision to change to grind saved several workings days. As calculated, the project must have reach substantial completion on 04/30. The request I received from you was on May 1, 2015. Even if additional days were to be granted for the previously planned added pavement repair I don’t see how the work could have been completed on time.

Please also show all bid items such as; A-8 and B-11 deleted and show a credit.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Tuesday, May 05, 2015 2:36 PM

To: 'Curtis Cooksey'

Cc: 'Jennifer Cline'

Subject: RE: Heintz Street - Digouts & paving

Hi Curtis,

Attached you will find Change Order #7 reflecting the grinding cost you provided below. Please sign and forward a copy to Jen for the City’s signature.

Thanks,

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Friday, April 17, 2015 4:18 PM

To: Jennifer Cline

Cc: hai@curran-mcleod.com

Subject: RE: Heintz Street - Digouts & paving

Hi Jennifer,

To grind Heintz st. @ 3” it will be $11,870.00

To pave Heintz 3” 514 ton+- @ $75.00 a ton $38,550.00

Total for Heintz $50,420.00

To grind Grange 3” @ 32’ wide it will be $18,055.00

To Pave Grange 3” 785 ton+- @ $75.00 a ton $58,875.00

Total for Grange $76,930.00

Total for both streets to grind and pave back the 3” $127,350.00

Deduct Item B-2 Pavement Repairs 2060 SY $21,939.00+

Deduct Item B-11 Geotextile Fabric 9000 SY $24,750.00

Let me know if you have any questions

Curtis

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Friday, April 17, 2015 10:57 AM

To: Hassan Ibrahim

Cc: Dan Huff; Curtis Cooksey

Subject: Heintz Street - Digouts & paving

Importance: High

Hi Hassan,

Dan and I went out to Heintz today looking at the planned dig-outs. The actual pavement failure well exceeds the planned dig-outs and extends from N Molalla to Grange. Our proposal is to do the following:

1. Prep trenches

2. Continue to grind 2” at curb line for 6 ft

3. Grind center roadway 3” for 28 ft

4. Place fabric for separation with in the 28 ft

5. Pave back 3” of PG 64-22, Level 3

6. Overlay 2” as planned

I believe this will save time and cost, and produced a better product for the City.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image