From: Jennifer Cline

Sent: Tue Sep 29 13:30:27 2015

To: Gerald Fisher

Subject: RE: FY 15-16 Budget - Water CIP

Importance: Normal

Attachments: Molalla_PW_CIP_Budget_2015-2021.xlsx;

 

Hi Gerald,

See the attached Water CIP section.

Where is the $125K number?

For the shared costs items, the amount under water is for the water portion of the project only. If that makes sense?

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Gerald Fisher [mailto:geraldf@pdgnw.com]

Sent: Monday, September 28, 2015 4:33 PM

To: Jennifer Cline <jcline@cityofmolalla.com>

Subject: FY 15-16 Budget - Water CIP

Hi Jennifer,

What is the breakdown for Water Capital Projects $125,000? The CIP has $100K for Metzler, $65K for Lola Ave, and $40K for 300 water meters.

Regards,

Gerald Fisher, PE | Senior Project Manager

PROJECT DELIVERY GROUP, LLC | 3150 22nd Street SE; Salem, OR 97302

www.PDGNW.com | 503-364-4004 (O) | 503-679-9237 (C)

** CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.