Our main crew member Adam will be out on Friday, but a short meeting with manufacturer for a few hours in the morning would be helpful for Garrett and myself.

Rob – Lets keep our schedule as planned regarding the installs and training (Wed & Thurs). If you want to join us on Friday for a few hours that would be great, but I understand if you have other work to do.

Thanks All!

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Lee, Rob [mailto:roblee@BrwnCald.com]

Sent: Thursday, January 15, 2015 9:46 AM

To: Ken Navidi; 'Jennifer Cline'

Cc: 'Garrett Edmunds'

Subject: RE: Flow Meters Install

I’m free on Friday during that time as well.

Robert Lee

Brown and Caldwell

roblee@brwncald.com

T 503.977.6625 | C 503.828.7542

From: Ken Navidi [mailto:knavidi@bainbridgeassoc.com]

Sent: Wednesday, January 14, 2015 4:38 PM

To: 'Jennifer Cline'

Cc: Lee, Rob; 'Garrett Edmunds'

Subject: RE: Flow Meters Install

Jennifer,

I have Wednesday afternoon open, so I’d be available to help with startup & training, I do not do manhole entry’s so you will need someone to climb in the hole…

If you can wait till Friday AM, Dan Ides with Hach Company who performs all Hachs DDS installations will be in town from Loveland, CO. You’d have both of us on Friday 8am – 1pmish. Dan is Hach’s is one of Hach’s experienced service person. He’d be a good asset to have during installs and help with training.

Ken Navidi

Bainbridge Associates Inc.

(503) 697-9711

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Wednesday, January 14, 2015 9:30 AM

To: 'Ken Navidi'

Cc: Lee, Rob; Garrett Edmunds

Subject: Flow Meters Install

Hi Ken,

The City will be installing the flow meters starting next Wednesday in the afternoon with Rob Lee. I know the quote we received indicates a start-up a training session. Will a technician be available on site to help with the installations next week?

We plan to start with the training and installation on 1/21 at noon, meeting at the City Shop, 920 Toliver Rd and continue onto Thursday to finish the installations.