From: Jennifer Cline

Sent: Tue Dec 30 14:31:12 2014

To: Ken Navidi

Cc: Dan Huff; Heather Penni; Garrett Edmunds

Subject: RE: Flow Meters for Molalla

Importance: Normal

Attachments: PO_CityofMolalla.pdf;

 

Hi Ken,

Attached is my request to place the purchase order for the included quote. Please let me know if you have any other questions.

Regards,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Ken Navidi [mailto:knavidi@bainbridgeassoc.com]

Sent: Wednesday, December 24, 2014 11:55 AM

To: 'Jennifer Cline'

Subject: RE: Flow Meters for Molalla

Jennifer,

Attached is your new quote including 1 wireless logger.

Happy Holidays

Ken Navidi

(503) 697-9711

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Wednesday, December 24, 2014 8:50 AM

To: Ken Navidi

Subject: RE: Flow Meters for Molalla

Hi Ken,

Thank you for the quote. Does this include the 1 wireless?

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Ken Navidi [mailto:knavidi@bainbridgeassoc.com]

Sent: Tuesday, December 23, 2014 10:17 PM

To: 'Jennifer Cline'

Cc: 'Lee, Rob'; 'Garrett Edmunds'

Subject: RE: Flow Meters for Molalla

Jennifer,

Attached is your quote for 7 direct connect flow meters with bands for pipe sizes below.

I called Hach and they said 2-3 weeks for delivery upon order, they suggested getting the order to us this week.

Let me know if you have any questions.

Ken Navidi

Bainbridge Associates Inc.

(503) 697-9711

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Monday, December 22, 2014 4:06 PM

To: 'Ken Navidi'

Cc: Lee, Rob; Garrett Edmunds

Subject: Flow Meters for Molalla

Hi Ken,

To follow up with my voicemail today, we recently were able to further define meter locations and our needs. We know we will need 7 Total meters; (6) manual reads and (1) wireless. Regarding the wireless, we are looking for a radio read versus an online monitoring data system. Is that option available?

Another question, what is the actual delivery time? I see the quotes states 6 weeks. Is it possible to have these in 2 week? I would rather not push this out to next season.

Here are the sizes of the pipes (specifically the highlighted pipe size) of the manholes we have decided to use for monitoring:

#1 - 12" PVC into 12" PVC

#2 - 12" PVC into 12" PVC, 15" PVC bypass line enters AND 15" PVC Bear Creek bypass line exits

#3 - 8" concrete into 8" concrete

#4 - 8" concrete into 8" concrete

#5 - 10" concrete into 10" concrete

#6 - 10" concrete into 10" concrete -

Note - where the Heinz and Grange lines meet it becomes 12"

#7 - 15" concrete Into 15" concrete - 12" concrete? From east (BC_A)

Please call me at your earliest convenience. I will be in the office most of tomorrow and Wednesday morning.

Happy Holidays!!!

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C: