From: Jennifer Cline

Sent: Mon Jun 06 16:24:36 2016

To: Dan Foeller

Cc: Nicolas Lennartz

Subject: RE: Fenton St_ ROW improvement bid and Water Line replacement estimate

Importance: Normal

 

Hi Dan,

Sorry I was out of the office when you called. Yes, Nicolas and I will be working on it starting tomorrow.

I will let you know if something comes up and we have any questions.

Have a good night.

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Dan Foeller [mailto:dan.foeller@carletonhart.com]

Sent: Monday, June 06, 2016 12:38 PM

To: 'Jennifer Cline' <jcline@cityofmolalla.com>; 'Nicolas Lennartz' <nlennartz@cityofmolalla.com>

Subject: FW: Fenton St_ ROW improvement bid and Water Line replacement estimate

Jennifer, Nicolas,

Does everything ok? Will the Permit Ready letter be available this week?

dan foeller, aia, LEED AP | project manager | 503.206.3195

CARLETON HART ARCHITECTURE PC

830 sw10th ave #200, portland or 97205

From: Dan Foeller

Sent: Wednesday, June 01, 2016 5:27 PM

To: 'Jennifer Cline'; 'Nicolas Lennartz'

Cc: 'Mai Huynh-Carnes'; Trell Anderson_CC; Mary Bradshaw; 'Sandra Perez'; Jacob Heitzman; Brian Carleton; Devin Follingstad; Amanda Morgan; 'Ken Bello'; Kyle Anderson; HDG (william.brannan@hdgpdx.com); 'Matthew Hlavaty'

Subject: Fenton St_ ROW improvement bid and Water Line replacement estimate

Jennifer,

We have some pricing for you.

Attached are the Fenton half-street ROW Improvement bid from LMC Construction and the Fenton water line replacement estimate from Humber Design Group.

The prices correlate to the Delta 5 Civil permit revision set dated 5/23/16

Please let me know if you have any questions.

Thanks

dan foeller, aia, LEED AP | project manager | 503.206.3195

CARLETON HART ARCHITECTURE PC

830 sw10th ave #200, portland or 97205