Do we have a chain of custody plan?
· Sample Chain of Custody Procedures-ensure that samples are protected and properly handled so as to preclude contamination from the sampling process.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Jason Clifford [mailto:jclifford@cityofmolalla.com]
Sent: Friday, June 26, 2015 8:45 AM
To: Jennifer Cline
Subject: RE: ERP - relationship between other plans
Hi Jennifer,
I’ve seen ERP’s with terrorist incidents, confined space issues as well
Jason
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Thursday, June 25, 2015 4:50 PM
To: Jason Clifford; 'Jonathan Patrick'
Subject: ERP - relationship between other plans
Hi,
Are either of you aware of any other plans procedures the plant may have on guidelines on to follow when certain situations arise. Here is a list of examples. I know we have the MSD sheets. I would like to list them as a reference in the ERP.
Examples of other guidelines and plans that may be present at a wastewater system include:
· Pretreatment or Industrial Discharge Sampling Plans-provide sampling procedures and protocol that can be used on suspect wastewater.
· Risk Management Plans-contain responses to hazardous chemical releases.
· Material Safety Data Sheets-standard data sheets that contain specific information regarding chemical characteristics and responses to chemical releases and exposures.
· Sample Chain of Custody Procedures-ensure that samples are protected and properly handled so as to preclude contamination from the sampling process.
· RCRA Hazardous Waste Contingency Plans-contain responses to hazardous waste spills and incidents for Large Quantity Generators of hazardous waste.