From: Jennifer Cline

Sent: Thu May 12 17:08:50 2016

To: Marc McKee

Cc: Peggy Johnson; Adam Shultz; Hash, Kenneth F.; Dennis Welle; Buehler, John A.

Subject: RE: Check/Diamond Cutting

Importance: Normal

Attachments: 15230 - Molalla Urban Renewal - Grout Submittal 001.pdf;

 

Hi Marc,

The 30 minutes is just the set time. What we are looking to achieve is the 24-hour compressive strength.

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Marc McKee [mailto:Marc@kodiakco.com]

Sent: Thursday, May 12, 2016 10:05 AM

To: 'Jennifer Cline' <jcline@cityofmolalla.com>

Cc: 'Peggy Johnson' <pjohnson@cityofmolalla.com>; 'Adam Shultz' <ashultz@cityofmolalla.com>; 'Hash, Kenneth F.' <HashK@hdjdg.com>; 'Dennis Welle' <dwelle@cityofmolalla.com>; 'Buehler, John A.' <BuehlerJ@hdjdg.com>

Subject: RE: Check/Diamond Cutting

Grout Submittal Attached. This product actually has a 30 minute cure time. This would allow us to reset all manholes on the 18th and then patch back that same day. Can this be approved? Sorry I was not aware of such a product when I sent my previous email requesting 17th construction/18th pave back on these…

I asked our General Construction superintendent and he indicated that they would be using just the grout and concrete dobie blocks for elevation changes. We don’t know what the metal spacers are. Hopefully Dobie blocks will work for you guys?

Thank you,

Marc McKee

Kodiak Pacific Construction

C(503) 880-2035 O(503) 783-4305

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Thursday, May 12, 2016 9:29 AM

To: Marc McKee

Cc: Peggy Johnson; Adam Shultz; Hash, Kenneth F.; Dennis Welle; Buehler, John A.

Subject: RE: Check/Diamond Cutting

Hi Marc,

Thank you for the update. I will have Adam set the meter once we receive the check.

In regards to the diamond cut, since this project was built from ODOT standards, I will defer to their standards. Please see ODOT standard drawing, Manhole Frame Adjustment RD360 Method “C”, with the exception of #4 bars and PCC. The #4 bars and PCC may be eliminated and PCC replaced with AC.

Please Note: Install metal spacers with non-shrink grout and allow minimum 24 hour cure. Please provide submittal for the spacers and non-shrink grout.

Thanks,

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Marc McKee [mailto:Marc@kodiakco.com]

Sent: Wednesday, May 11, 2016 5:20 PM

To: 'Jennifer Cline' <jcline@cityofmolalla.com>

Subject: Check/Diamond Cutting

The check for the meter will be mailed tomorrow.

Is there a specific size or parameter we are cut for the diamond cutting around the manholes?

Thank you,

Marc McKee

Kodiak Pacific Construction

C(503) 880-2035 O(503) 783-4305