From: Jennifer Cline

Sent: Thu Feb 12 08:57:39 2015

To: Curtis Cooksey; hai@curran-mcleod.com

Cc: Dan Huff; Heather Penni

Subject: RE: Change Order #2

Importance: Normal

Attachments: EE_ChangerOrderNo.2_Signed.pdf;

 

Attached is the approved Change Order #2. This Change Order has been approved by council on 02/12/2013.

Please proceed with the order of materials and work.

Thanks,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Friday, February 06, 2015 10:46 AM

To: hai@curran-mcleod.com

Cc: jcline@cityofmolalla.com

Subject: RE: Change Order #2

Hassan,

Here you go.

Thanks

Curtis

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Friday, February 06, 2015 8:03 AM

To: Curtis Cooksey

Cc: 'Jennifer Cline'

Subject: RE: Change Order #2

Hi Curtis,

Thanks for revising the water cost proposal as requested ( deleting the EC cost), please sign and forward to Jennifer to obtain the City signature.

Thanks,

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com