From: Jennifer Cline
Sent: Thu Feb 05 10:40:09 2015
To: hai@curran-mcleod.com
Cc: Heather Penni; Dan Huff
Subject: RE: Change Order #2
Importance: Normal
Attachments: Eagle_Elsner006.pdf; Hi Hassan, I have a few concerns with their estimate, let me know what you think? 1) The Mob seems a bit high to me. It is calculated at approx. 8.4% when they are already on the job. 2) The traffic control is also high. If they are planning to close the road to do the work there should be minimal cost for TTC with no flagging. Also, will other work be going on during this time? I’m calculating just over half their quote for 30 days of a full street closure. 3) What is the breakdown for erosion control? Erosion control should already be in place. Thanks, Jennifer Cline, P.E. City of Molalla Public Works Director O: 503.759.0218 F: 503.829.3676 From: Curtis Cooksey [mailto:curtis@eagle-elsner.com] Sent: Thursday, February 05, 2015 8:32 AM To: hai@curran-mcleod.com Cc: jcline@cityofmolalla.com Subject: RE: Change Order #2 Hi Hassan, Here you go. Thanks Curtis From: Hassan Ibrahim [mailto:hai@curran-mcleod.com] Sent: Thursday, February 05, 2015 8:02 AM To: Curtis Cooksey Cc: 'Jennifer Cline' Subject: RE: Change Order #2 <<...>> Hi Curtis, Here is CO #2. Please sign and forward to the City for their signature. Thanks, -------------------- Hassan Ibrahim, P.E. CURRAN-McLEOD, INC. 6655 SW Hampton St, Ste. 210 Portland, OR 97223 Tel: 503-684-3478 Fax: 503-624-8247 Cell: 503-807-2737 email: hai@curran-mcleod.com