From: Jennifer Cline

Sent: Thu Feb 05 10:40:09 2015

To: hai@curran-mcleod.com

Cc: Heather Penni; Dan Huff

Subject: RE: Change Order #2

Importance: Normal

Attachments: Eagle_Elsner006.pdf;

 

Hi Hassan,

I have a few concerns with their estimate, let me know what you think?

1) The Mob seems a bit high to me. It is calculated at approx. 8.4% when they are already on the job.

2) The traffic control is also high. If they are planning to close the road to do the work there should be minimal cost for TTC with no flagging. Also, will other work be going on during this time? I’m calculating just over half their quote for 30 days of a full street closure.

3) What is the breakdown for erosion control? Erosion control should already be in place.

Thanks,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Thursday, February 05, 2015 8:32 AM

To: hai@curran-mcleod.com

Cc: jcline@cityofmolalla.com

Subject: RE: Change Order #2

Hi Hassan,

Here you go.

Thanks

Curtis

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Thursday, February 05, 2015 8:02 AM

To: Curtis Cooksey

Cc: 'Jennifer Cline'

Subject: RE: Change Order #2

<<...>>

Hi Curtis,

Here is CO #2. Please sign and forward to the City for their signature.

Thanks,

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com