From: Jennifer Cline

Sent: Thu Feb 05 14:42:50 2015

To: Curtis Cooksey

Cc: Hassan Ibrahim; Heather Penni; Dan Huff

Subject: RE: Change Order #2

Importance: Normal

 

Hi Curtis,

Please see my comments below in Red.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Thursday, February 05, 2015 1:53 PM

To: jcline@cityofmolalla.com

Cc: hai@curran-mcleod.com

Subject: RE: Change Order #2

Hi Jennifer,

1) The Mobilization Item covers Mikes time (Supervision)for the added work and additional Bond and Insurance, No equipment moves were included. Agreed

2) The Traffic Control Item covers a flagger to set up and take down signs and barricades every day. Even with the closure, we will still have to get people in and out of the area to their homes with open trenches.

We will have to finish the water line and services on Stowers before we can core the street and prep for curbs and asphalt.

3) The erosion control is for dewatering the trench. Agreed

The measurement and payment section for Erosion Control (Item A-3) does not include payment for dewatering for utility trench work. Also, Section 02200, Part 3.08 address Groundwater and states that it is incidental to the to the contract.

Please remove the cost for the Erosion Control and I will work to have the change order signed.

Let me know if you have any more question.

Thanks

Curtis

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Thursday, February 05, 2015 11:25 AM

To: Curtis Cooksey

Subject: FW: Change Order #2

Hi Curtis,

Can you elaborate on Jennifer’s concerns?

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Thursday, February 05, 2015 10:40 AM

To: hai@curran-mcleod.com

Cc: Heather Penni; Dan Huff

Subject: RE: Change Order #2

Hi Hassan,

I have a few concerns with their estimate, let me know what you think?

1) The Mob seems a bit high to me. It is calculated at approx. 8.4% when they are already on the job.

2) The traffic control is also high. If they are planning to close the road to do the work there should be minimal cost for TTC with no flagging. Also, will other work be going on during this time? I’m calculating just over half their quote for 30 days of a full street closure.

3) What is the breakdown for erosion control? Erosion control should already be in place.

Thanks,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]

Sent: Thursday, February 05, 2015 8:32 AM

To: hai@curran-mcleod.com

Cc: jcline@cityofmolalla.com

Subject: RE: Change Order #2

Hi Hassan,

Here you go.

Thanks

Curtis

From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]

Sent: Thursday, February 05, 2015 8:02 AM

To: Curtis Cooksey

Cc: 'Jennifer Cline'

Subject: RE: Change Order #2

<<...>>

Hi Curtis,

Here is CO #2. Please sign and forward to the City for their signature.

Thanks,

--------------------

Hassan Ibrahim, P.E.

CURRAN-McLEOD, INC.

6655 SW Hampton St, Ste. 210

Portland, OR 97223

Tel: 503-684-3478

Fax: 503-624-8247

Cell: 503-807-2737

email: hai@curran-mcleod.com