From: Jennifer Cline
Sent: Fri Feb 06 11:02:53 2015
To: Dan Huff
Cc: Heather Penni
Subject: RE: Change Order #2
Importance: Normal
I gave this to her yesterday, I will follow up with her.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Dan Huff [mailto:dhuff@cityofmolalla.com]
Sent: Friday, February 06, 2015 11:00 AM
To: Jennifer Cline
Subject: RE: Change Order #2
Yes. Has Heather worked this into her current financial forecast?
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Friday, February 06, 2015 10:57 AM
To: Dan Huff
Cc: Sadie Cramer; Heather Penni
Subject: FW: Change Order #2
I’m assuming this needs to go in front of council due to the price tag?
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Curtis Cooksey [mailto:curtis@eagle-elsner.com]
Sent: Friday, February 06, 2015 10:46 AM
Subject: RE: Change Order #2
Hassan,
Here you go.
Thanks
Curtis
From: Hassan Ibrahim [mailto:hai@curran-mcleod.com]
Sent: Friday, February 06, 2015 8:03 AM
To: Curtis Cooksey
Cc: 'Jennifer Cline'
Subject: RE: Change Order #2
Hi Curtis,
Thanks for revising the water cost proposal as requested ( deleting the EC cost), please sign and forward to Jennifer to obtain the City signature.
Thanks,
--------------------
Hassan Ibrahim, P.E.
CURRAN-McLEOD, INC.
6655 SW Hampton St, Ste. 210
Portland, OR 97223
Tel: 503-684-3478
Fax: 503-624-8247
Cell: 503-807-2737
email: hai@curran-mcleod.com