From: Jennifer Cline

Sent: Mon May 02 14:49:15 2016

To: Alan McCall

Cc: Gerald Fisher; Nicolas Lennartz

Subject: RE: Catch Basin Question

Importance: Normal

 

Hi Alan,

An storm system in line with the catch basins is not a standard design for the City of Molalla. What project is this in reference to? This may be something you propose with your design that the City can approve.

Regards,

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Alan McCall [mailto:amccall@cesnw.com]

Sent: Monday, May 02, 2016 2:38 PM

To: jcline@cityofmolalla.com

Subject: Catch Basin Question

Hi Jennifer,

I was not able to find any information regarding if a catch basin line can be stubbed directly into the mainline without a manhole. Is this allowed in the City?

Thank you,

Alan McCall, EIT, LSIT

CES|NW, Inc.

13190 SW 68th Parkway, Suite 150

Tigard, OR 97223

Office: 503 – 968 – 6655

www.cesnw.com