From: Jennifer Cline

Sent: Thu May 12 17:42:39 2016

To: Tendick, Randall

Cc: chris.link@msa-ep.com; Sarah Kennedy

Subject: RE: BOLI/PWR: Request for completion of WH-81 form

Importance: Normal

Attachments: ML Houck 1st Tier Sub Disclosure.pdf; 2015-11-25_DJC_AffidavitOfPublication.pdf; image001.jpg;

 

Hi Randall,

The date has been added.

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Tendick, Randall [mailto:randall.tendick@state.or.us]

Sent: Thursday, May 12, 2016 4:37 PM

To: dpw@cityofmolalla.com

Subject: BOLI/PWR: Request for completion of WH-81 form

Jennifer, I received your WH-81 form with an important date missing on it. If your project wasn’t advertised then use the alternate dates (RFP or first contact with contractor). This date is required because it’s the date that is used to determine which prevailing wage rate surveyed date to use for the project.

Please enter a date in the highlighted field of the attached WH-81 form and resubmit forms to me via this email.

Thank you

Randall L. Tendick

Administrative Specialist 1 (fees)

image

Bureau of Labor & Industries

Prevailing Wage Rate (WHD)

Phone: 971-673-0852

Fax: 971-673-0769

Randall.Tendick@state.or.us

Date contract specification First Advertised for bid

(if not advertised, date of RFP (Request for proposal/price)

RFQ (Request for Quote) or First Contact with contractor.

Applicable Rate for Public Works Projects:

Generally, the applicable prevailing wage rates for a

public works project are those in effect at the time

the initial specification are first advertised for bid

solicitations by the public agency. The rates in effect at

that time are the rates that are to be used for the duration

of the project.