Depends on the thickness of the AC and width of the road. All vary on the project.
Typical section
(40’ wide)*(4” Thick)* 1mi(5280’/mi) = 70,400 cf/(27cf/cy) = 2,607 cy * 2.05 Ton/cy = 5,345 Tons in a typical roadway section for 1mile
Stowers, Grange & Heintz, plus additional patch work = 280,663 tons @ $75,00
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Dan Huff [mailto:dhuff@cityofmolalla.com]
Sent: Thursday, May 28, 2015 3:50 PM
To: Jennifer Cline
Subject: FW: Asphalt
See?
From: dpearson@canbyherald.com [mailto:dpearson@canbyherald.com]
Sent: Thursday, May 28, 2015 3:49 PM
Subject: RE: Asphalt
Thanks, Dan. So, how many tons in 1/10th Of a mile?
Daniel
From: Dan Huff [mailto:dhuff@cityofmolalla.com]
Sent: Thursday, May 28, 2015 3:41 PM
To: Daniel Pearson
Subject: Asphalt
$75 per ton. Price associated with our recently completed projects.