Depends on the thickness of the AC and width of the road. All vary on the project.

Typical section

(40’ wide)*(4” Thick)* 1mi(5280’/mi) = 70,400 cf/(27cf/cy) = 2,607 cy * 2.05 Ton/cy = 5,345 Tons in a typical roadway section for 1mile

Stowers, Grange & Heintz, plus additional patch work = 280,663 tons @ $75,00

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Dan Huff [mailto:dhuff@cityofmolalla.com]

Sent: Thursday, May 28, 2015 3:50 PM

To: Jennifer Cline

Subject: FW: Asphalt

See?

From: dpearson@canbyherald.com [mailto:dpearson@canbyherald.com]

Sent: Thursday, May 28, 2015 3:49 PM

To: dhuff@cityofmolalla.com

Subject: RE: Asphalt

Thanks, Dan. So, how many tons in 1/10th Of a mile?

Daniel

From: Dan Huff [mailto:dhuff@cityofmolalla.com]

Sent: Thursday, May 28, 2015 3:41 PM

To: Daniel Pearson

Subject: Asphalt

$75 per ton. Price associated with our recently completed projects.