From: Jennifer Cline
Sent: Fri Apr 17 07:59:47 2015
To: Hassan Ibrahim
Subject: Re: Additional C.O requests
Importance: Normal
I don't think the storm drain repair was 10". Please verify w Bob.
Sent from my iPhone
> On Apr 17, 2015, at 6:33 AM, Hassan Ibrahim <hai@curran-mcleod.com> wrote:
>
> Hi Curtis,
>
>
>
> As per the City's request attached please find the location of the proposed
> changes, also see below our responses in red.
>
>
>
> Should you have any questions, please let me know.
>
>
>
> Thanks,
>
> --------------------
> Hassan Ibrahim, P.E.
> CURRAN-McLEOD, INC.
> 6655 SW Hampton St, Ste. 210
> Portland, OR 97223
> Tel: 503-684-3478
> Fax: 503-624-8247
> Cell: 503-807-2737
> email: hai@curran-mcleod.com
>
>
>
> From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
> Sent: Thursday, April 16, 2015 2:59 PM
> To: Hassan Ibrahim
> Cc: 'Curtis Cooksey'; Dan Huff; Heather Penni; Dennis Welle; 'Adam Shultz'
> Subject: Additional C.O requests
>
>
>
> Hi Hassan,
>
>
>
> The City would like to request a change order for the 3 additional items.
>
>
>
> . Storm drain pipe repair from the catch basin located at the NE
> corner of 6th St and Stowers Ave. This can be paid under 10" DI Pipe as per
> CO#5 @$47.10/ LF. However, it can be included as a line item in a new CO #7.
>
> . Construct a new storm Type G-2 Basin at the NW corner of 7th and
> Stowers and connecting it to the storm main in 7th St. There is nowhere for
> the water flowing to the south to drain. The next nearest storm basin is on
> 7th and Cole at least 100 yards away with almost 0% slope in some areas.
> This can be paid under 10" DI Pipe as per CO#5 @$47.10/ LF. However, it can
> be included as a line item in a new CO #7.
>
> . Add a water valve at Heintz and Kennel for the south main on
> Kennel. There currently is no ability to shut off the water south on Kennel
> without turning off other users water as well. 1 existing valve is to be
> abandoned as well. Need a price for this one.
>
> . Add 1 day to the schedule for determining the driveway conflicts
> on Stowers. I am thinking 2 days (one for the storm work and one for the
> valve installation)
>
>
>
> Jennifer Cline, P.E.
>
> City of Molalla
>
> Public Works Director
>
> O: 503.759.0218
>
> F: 503.829.3676
>
>
> <file:///C:\Users\jsherman\AppData\Roaming\Microsoft\Signatures\jennifer%20c
> line_files\Image001.jpg>
>
> <Stowers Changes.pdf>