From: Jennifer Cline

Sent: Thu Jul 30 10:28:43 2015

To: Nicolas Lennartz

Subject: RE: Access & Driveway Construction

Importance: Normal

 

He wants to be treated “fair” but doesn’t do the work.  J

Hope your day goes better and is SH-less.  I too know your pain!!

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F:  503.829.3676

image "file:///C:

From: Nicolas Lennartz [mailto:nlennartz@cityofmolalla.com]

Sent: Thursday, July 30, 2015 9:40 AM

To: psmall@pacnorthinvest.com

Cc: Jennifer Cline <jcline@cityofmolalla.com>

Subject: Access & Driveway Construction

Good morning Philip,

 

I’ve been looking for the access permits that you mentioned you had submitted, and I can’t seem to find any. Without this permit, we are unable to perform any inspections. Jennifer had sent you some information on the access construction back in December.

 

If this is the case that these were never submitted, please fill out a permit for each access construction and return to me. We will perform the inspection within 24 hours.

 

Thanks,

Nicolas Lennartz | Community Planner | City of Molalla

O: 503∙759∙0219 | C: 503∙998∙7048

communityplanner at cityofmolalla.com

117 N. Molalla Ave. | Molalla, OR 97038