From: Jennifer Cline

Sent: Mon Jun 01 16:46:58 2015

To: Gerald Fisher

Cc: Nicolas Lennartz

Subject: RE: 15078 Draft deep service standard detail

Importance: Normal

Attachments: 15078 Deep Sewer Service.pdf;

 

Hi Gerald,

Only thing I see it note 2, City PW does not need to tap the main. However, tap at the main must be inspected prior to backfill. Otherwise, this looks good. I will pass this along to our PW supervisor for comment as well.

Thanks,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Gerald Fisher [mailto:geraldf@pdgnw.com]

Sent: Monday, June 01, 2015 3:22 PM

To: Jennifer Cline

Subject: 15078 Draft deep service standard detail

Hi Jen,

Please see attached draft detail for your review. Redline any comments or changes you have and email them back to me once complete. We will need to discuss a hierarchy for the detail drawings and can select from other agencies as needed.

Here is a link to Salem’s. http://www.cityofsalem.net/DEPARTMENTS/PUBLICWORKS/ENGINEERING/Pages/Publications.aspx Let me know if this looks good to you and we can use it going forward. It allows for 100 details per section. Thanks.

Regards,

Gerald Fisher, PE | Senior Project Manager

PROJECT DELIVERY GROUP, LLC | 3150 22nd Street SE; Salem, OR 97302

www.PDGNW.com | 503-364-4004 (O) | 503-679-9237 (C)

** CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.