Hi Gerald,

Thank you for the updates. Let’s set a time to meet when you come back from vacation. Also, feel free to send over your services contract and I will look it over.

Thanks again,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Gerald Fisher [mailto:geraldf@pdgnw.com]

Sent: Monday, March 16, 2015 2:22 PM

To: Jennifer Cline

Cc: Dan Huff; Nicolas Lennartz

Subject: RE: 15043 Molalla Public Works Standards (Revised)

Hi Jennifer,

I modified the assumption to 10 days in the proposal and made the edits to the proposed schedule for the 10 day review time and starting the optional tasks after July 01. No problem if your folks need more than 10 days due to workload. I will keep working on the items in Task 1 and we’ll catch up as time allows in your schedule. I’ll keep track of our progress during the project so we have an idea of end dates for Task 1. Let me know if you want to use your contract documents for this project or I can send you our services contract, whatever is easiest. Once executed, I will start work on Section 1.

I am headed down to the APWA conference in Eugene Wednesday thru Friday and will be out of the office on a short vacation next Monday & Tuesday. No other planned days off until around August. Thanks again Jennifer.

Regards,

Gerald Fisher, PE | Senior Project Manager

PROJECT DELIVERY GROUP, LLC | 3150 22nd Street SE; Salem, OR 97302

www.PDGNW.com | 503-364-4004 (O) | 503-679-9237 (C)

** CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Friday, March 13, 2015 4:57 PM

To: Gerald Fisher

Cc: Dan Huff; Nicolas Lennartz

Subject: RE: 15043 Molalla Public Works Standards

Hi Gerald,

Finally I had a moment to read through the Project Description. Here are my comments, Dan may have some as well.

· Scopes 1 – 4 look acceptable to me. However, budget wise the can only commit to Scope 1 for this FY, in July we can begin the Scopes 2-4

· 5. City Code Modification – We definitely want to do this, however we are currently working with DLCD to overhaul the entire code. I know there will be a comment period and that’s when it will be appropriate time to review the draft and comment. I’m don’t have a good feel when that may be.

· 6. Public Process – Will follow Scope 5 when appropriate.

· Assumptions 3. Please provide me with up to 10 business days. It may not take me 10 days, but we are short staffed at this time and paving is coming up soon which will require more of my time for sure.

· Assumptions 4. I agree to adopt DEQ standards for new construction of lift stations.

Appreciate you taking the time to put this Scope and Budget together.

Looking forward to working with you on these projects,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Gerald Fisher [mailto:geraldf@pdgnw.com]

Sent: Tuesday, March 10, 2015 9:54 AM

To: Jennifer Cline

Subject: 15043 Molalla Public Works Standards

Hi Jennifer,

Please see attached proposal for development of a the public works standards for Molalla. Preparation of standards can take up to approximately one year when starting from scratch but since I have already worked on standards for other agencies, I’m sure we can complete the written format before the end of this fiscal year. Other items listed as optional can be done as time and funding allows with the goal of adopting a set of standards and then ultimately operating independently from state agency review. Let me know if you have any questions or want to discuss approach and alternatives. Thanks again for the opportunity.

Regards,

Gerald Fisher, PE | Senior Project Manager

PROJECT DELIVERY GROUP, LLC | 3150 22nd Street SE; Salem, OR 97302

www.PDGNW.com | 503-364-4004 (O) | 503-679-9237 (C)

** CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.