Hi Gerald,

We are requesting cost proposals to correct the floor failure around the post bottom that connects to the floor of the filter. I have provided a few pictures and the filter design plans, although not much detail is given on the post locations. In addition, we will need to have the entire subfloor area covered with an epoxy paint to prevent this from happening again in the future. There is also a possibility to have filter #3 inspected and repaired this summer as well.

https://www.dropbox.com/sh/024dp9n73vvf8rq/AADLRFbJTKv3_jRCk22Reno4a?dl=0

Please forward this proposal request to Rob McClure to see if they would be interested in submitting their costs to make the repairs.

We would like to schedule the work just after July 1.