From: Jennifer Cline
Sent: Fri Sep 18 11:32:55 2015
To: Jason Clifford
Cc: Jon Randall
Subject: Leak Test Guidelines & Biosolids report
Importance: Normal
Attachments: Appendix A_ODEQ Guidelines for Est Leakage from Exisiting Sewage Lagoons.pdf; Here’s a good clean copy I was able to find on the web. The one I had was copied a few times. Also, thanks for dropping off the folder with the Biosolids info and maps. Just a reminder, the annual Biosolids report deadline is due February 19th. There is an example from last year on the W:/ drive which I’m sure you are aware of as well. Let’s use the same process as with the Leak Test report. Thanks, Jennifer Cline, P.E. | Public Works Director Licensed in OR, WA 117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038 O: 503.759.0218 | F: 503.829.3676