From: Jennifer Cline

Sent: Wed Sep 02 17:16:29 2015

To: Phillip Bender; Lee, Rob

Cc: Dan Huff; 'Christine Hein'

Subject: I/I Plan Update w/ new schedule

Importance: Normal

Attachments: Updated_09-2015_FINAL_Molalla II Assessment and Reduction Plan.pdf; 2015_RFP_cctv_map.pdf;

 

Hi Phil,

Here is the updated I/I plan to reflect the schedule changes this year due to budgetary constraints.

The CCTV inspection work (including WWTP storm inspection) is going to run just under $100K to video about ½ the system. I have worked with Rob on the areas to target first. See attached map.

Smoke testing will also be completed next year in target locations.

I am planning to send this along to David Cole at DEQ tomorrow to be in compliance with both the consent decree and NPDES. Please let me know your thoughts.

Best,

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

image