From: Jennifer Cline

Sent: Wed Mar 09 10:38:51 2016

To: Nicolas Lennartz

Cc: Gerald Fisher

Subject: FW: Stone Place Phase 3

Importance: Normal

 

Jeff needs approval from the City, Gerald had a few comments to follow up on.

Thanks,

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Jeff Bolton [mailto:JBolton@mtengineering.net]

Sent: Wednesday, March 09, 2016 9:42 AM

To: 'Nicolas Lennartz' <nlennartz@cityofmolalla.com>

Cc: 'Jennifer Cline' <jcline@cityofmolalla.com>

Subject: Stone Place Phase 3

Good morning Nicolas,

Just wanted to give you an update on the private civil plans being reviewed by Clackamas County.

The private sanitary sewer and domestic water plans are approved. The storm drainage will be approved in a couple of days. We had some roof drain updates to be done and I should have these plans submitted back to the county this afternoon.

So in theory we could be pulling permits and starting up the private storm drainage later next week. Is there any reason from the city of Molalla’s viewpoint on why we could not start up this work???

I gave Jennifer a heads up yesterday, that we are going to start getting building plan approvals as well by the 1st of next week, although I do understand that I need to have the public sanitary and public fire line plan approval prior to having you (Nicolas) send me an approved site plan for the release of the building permits through the County.

Thanks,

Jeff Bolton

Multi/Tech Engineering