From: Jennifer Cline
Sent: Tue Dec 23 15:57:55 2014
To: Scott Hewett
Cc: Garrett Edmunds; Dan Huff
Subject: FW: Paving
Importance: Normal
Hi Scott,
This is typically a 5 minute meeting that a contractor holds before paving begins, usually with his crews. I never stated that the contractor doesn’t know what he’s doing. I understand this is a subdivision, however it is in the middle of a built out subdivision and I would like to see minimal impacts to the surrounding residents with trucks coming and leaving or parking in the street, including their public safety.
Regarding the City vs. State. The City still assumes ownership over a life time of the completed work and I want to ensure we receive a quality end paving project to keep future maintenance costs to a minimum. As for the meeting, I primarily stand and listen to what the contractor has to say when he begins his coordination with everyone involved.
Please understand this is in no way intended to delay the paving of the project.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Scott Hewett [mailto:scott.hewett23@gmail.com]
Sent: Tuesday, December 23, 2014 2:05 PM
To: Jennifer Cline
Subject: Re: Paving
Jennifer
Please understand this is not a requirement anywhere. We have all done this for a long time. This a subdivision and not a state project. The paver knows what he's doing. I am getting a lot of questions on why. I understand that you have your list of items. But everyone is trying their hardest to get this done and these little things are hard to justify.
Meeting the safety requirements is completed on all trucks for their annual inspection. If there is an issue DOT can dictate the reasoning.
It's all figured out. It just needs to get done.
Scott Hewett, President
Hewett Construction
PH: 971-246-0501
F: 503-628-1386
On Dec 23, 2014, at 1:39 PM, Jennifer Cline <jcline@cityofmolalla.com> wrote:
Meeting agenda should include these items, but not limited to:
· Safety info & precautions (i.e. all trucks should have functioning back up alarms, etc)
· How he plans to pave (start to finish), truck circulation and parking to avoid impacting surrounding residents.
· Traffic Control, bring Class B signs for Trucks leaving work zone
· Expected Rolling patterns to meet compaction
What is the total tonnage estimated for the development?
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Scott Hewett [mailto:scott.hewett23@gmail.com]
Sent: Tuesday, December 23, 2014 1:35 PM
To: Garrett Edmunds; Jennifer Cline
Subject: Re: Paving
Jennifer
I can get the paver to verify the mix design.
In regard to the meeting what is required? We would like to pave Monday and Tuesday. The testing co, Geopacific is on board. It all determines on the weather.
Due to the timing and the cost of having someone come out, we typically don't set up a paving meeting. We are all ready to go and trying to get everyone together with their schedules doesn't help. If there are specific issues I can email the appropriate people to help.
At this time, we are discussing in Friday to pave Monday.
Thank you
Scott Hewett, President
Hewett Construction
PH: 971-246-0501
F: 503-628-1386
On Dec 23, 2014, at 1:16 PM, Garrett Edmunds <gedmunds@cityofmolalla.com> wrote:
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Tuesday, December 23, 2014 12:54 PM
To: Garrett Edmunds
Subject: RE: Paving
Not at all
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Garrett Edmunds [mailto:gedmunds@cityofmolalla.com]
Sent: Tuesday, December 23, 2014 11:23 AM
To: Jennifer Cline
Subject: RE: Paving
Do you mind if I forward this to Scott?
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Tuesday, December 23, 2014 10:52 AM
To: Garrett Edmunds
Subject: RE: Paving
Hi Garrett,
He can pave if the following conditions can be met:
· A pre-paving meeting must be scheduled in advance and includes the contractor(himself), paving sub, testers and the City reps.
· The city needs to verify the mix design meets the Level 2, PG 64-22 - ½” Dense HMAC requirements (as stated on the plans), I need the JMF at least 24 hours in advance of the pre-paving meeting.
· Temperature must be 40 degrees minimum and rising measured on the rock/ground
· No standing water is allowed (puddles)
Also, ask him if he knows the tonnage to be placed to determine if the work can qualify under minor HMAC. I’m assuming not, but wanted to clarify.
Jennifer Cline, P.E.
City of Molalla
Public Works Director
O: 503.759.0218
F: 503.829.3676
From: Garrett Edmunds [mailto:gedmunds@cityofmolalla.com]
Sent: Tuesday, December 23, 2014 10:17 AM
To: Jennifer Cline
Subject: Paving
Hello,
I spoke with Scott Hewitt this morning about paving on 12-29 or 12-30. The weather repot says clear and cold 41/21. If it is that cold shall we tell them to hold off?
Thanks
Garrett Edmunds
Operation Division Supervisor
117 N Molalla Ave PO Box 248
Molalla, OR 97038
503-829-5401
503-829-3676(fax)